How to Comply with Notice Requirements for the Safe Construction Bill of Rights and Tenant Protection Plans

Suppose you are a general contractor, hired by a landlord to renovate the atrium of an apartment building in Bushwick. It looks like a simple job that will take a month, but it will generate significant noise and dust, and it will require interruption of the hot water and gas lines. In this case, you need to make sure that the landlord has provided sufficient notice to the occupants of the building.

In 2017, the New York City Council enacted a package of ordinances dubbed as the “Stand for Tenant Safety”. These laws were enacted to curb egregious abuses like the case of Daniel Melamed, a Crown Heights landlord so determined to evict rent-stabilized tenants that he hired contractors to perform illegal construction work. Melamed hired his contractors to conduct partial demolition of the building while tenants were still living in it, exposing tenants to friable asbestos and toxic concentrations of lead dust, and intentionally cutting off heat in the dead of the winter. The Attorney General filed criminal charges, and Melamed was ultimately convicted on three counts of unlawful eviction.

The City Council’s stated intent in enacting these new notice requirements is to provide tenants with relevant information when their Landlord conducts significant renovations in the building, and to deter the misuse of construction contractors for the ulterior purpose of harassing rent-stabilized tenants.

The Safe Construction Bill of Rights

One ordinance in the “Stand for Tenant Safety” package is Intro-960 sponsored by Rosie Mendez (D-Lower East Side), more colloquially known as the “Safe Construction Bill of Rights” (or in this legal alert, “SCBOR”). Substantively, the only thing that SCBOR does is establish an affirmative obligation for landlords to provide written notice to their tenants about any significant construction or renovations on the premises. It is a best practice for every contractor to take care that the landlord follows this new notice rule.  

In any such situation in which a Landlord’s obligations attach, the Landlord must make available a document titled the “Safe Construction Bill of Rights” to all of the Occupants (“SCBOR Notice”). For new buildings, the SCBOR Notice requirements attach whenever a landlord applies for a temporary certificate of occupancy. For existing buildings, the notice requirement attaches “contemporaneously” when a landlord applies for a work permit for any work significant enough that it requires a permit; i.e. anything more than mere “ordinary repairs” or “minor alterations”.  Note, however, that if the landlord applies for an emergency work permit, the notice requirement attaches “immediately.”

According to the Safe Construction Bill of Rights, the SCBOR Notice must inform occupants of the following information:

  1. A description of the construction work being conducted (“Work”)
  2. The location of the Work
  3. The projected timeline for completion of the Work
  4. A description of the services anticipated to be interrupted during the Work, such as hot water, an elevator, a stairwell, an entrance, etc.
  5. Contact information for an agent or an employee of the landlord who can be reached for emergency matters and non-emergency matters
  6. Contact information for 311 or other city or state agencies

The Landlord can comply with the Notice requirements by distributing the SCBOR Notice to each occupied dwelling unit. The Landlord can also comply by posting the SCBOR Notice “in a conspicuous manner” in the building lobby next to the Housing Information Guide required to be posted on every floor next to every elevator and every stairwell.

The Tenant Protection Plan

A separate ordinance, Intro-936-A, establishes the requirements of a valid Tenant Protection Plan (“TPP”). New York City landlords will also have to provide a TPP (“TPP Notice”) in any scenario in which there will be construction or demolition work in “buildings containing occupied dwelling units”. This includes buildings that are partially occupied while contractors are still conducting construction work elsewhere in the building.

At minimum, the TPP Notice must include specific, detailed provisions for:

  1. Egress. The TPP must include how tenants can exit the building during construction
  2. Fire Safety. The TPP must include how construction will comply with the Fire Code
  3. Health Requirements. The TPP must specify means and methods to be used to control dust, disposal of construction debris, pest control, maintenance of sanitary facilities, and limitation of noise. The TPP must include a statement of “means and methods” of compliance with applicable laws on lead and asbestos.
  4. Housing Code. The TPP must state how to comply with the NYC Housing Maintenance Code and the New York State Multiple Dwelling Law (if applicable)
  5. Structural Safety. The TPP must state that no structural work shall be done that may endanger the occupants.
  6. Noise Restrictions. The TPP must state the limitations where the hours of the day or days of the week in which construction work may be undertaken are limited pursuant to the NYC Noise Control Code.
  7. Maintaining Essential Services. The TPP must specify the “means and methods” to be used for maintaining heat, hot water, cold water, gas, electricity, or other utility services; if such “essential services” are anticipated to be disrupted, for how long what “means and methods” will be employed to minimize the disruption of “essential services”.

The TPP Notice must contain a statement that “the building contains dwelling units that will be occupied during construction” and must list those units. The TPP Notice must also include the specific “means and methods” which the contractor will employ to safeguard the safety and health of all occupants throughout the construction. You have to explain your safety and health procedures  with particular detail – a bare recitation of the law, or writing “legal” or “code compliant” will not suffice.

Once the TPP Notice responsibilities attach, the landlord will have to make the TPP Notice available to all of the tenants. The TPP Notice can also be distributed to each occupied dwelling unit, or posted “in a conspicuous manner” in the building lobby and on each floor next to the elevators or stairwells.  Landlords will have to use the DOB-approved form.  

In Practice

The next time you have to conduct any significant work on a residential building, make sure that the Landlord has complied with the Notice requirements of the Safe Construction Bill of Rights and a Tenant Protection Plan. Otherwise, DOB can issue fines to the landlord on the order of a Class 1 Violation – and if that happens, there is a good chance that many landlords are going to try to pin the blame on the contractor.

Remember that the Tenant Protection Plan is not a toothless notice requirement; it is a part of your “Contract Documents”. The owner must provide written notice to DOB at least 72 hours before the contractor commences any work requiring a TPP. The contractor is obligated to comply with the TPP upon issuance of work permits.

When drafting a contract, you may want to specifically provide that the landlord is obligating to provide due notice of the Safe Construction Bill of Rights and a Tenant Protection Plan to all tenants and to DOB. If you get to the job site, and you do not see the Notice posted at entrances, stairwells, and elevators, make sure to get in writing from the Landlord that Notice has been distributed directly to all of the tenants.

According to the ordinance, DOB is going to conduct inspections of at least 5 percent of all building sites to determine compliance with the TPP. DOB is also going to conduct inspections after receiving a complaint about any such work. If DOB determines that work is noncompliant with the approved TPP, DOB can issue a stop work order.

Be wary of contracting with unscrupulous landlords. If you have any reason to believe that a potential client has ulterior motives in hiring you to do construction work, think twice about signing that contract.

If you are already on the job site, and your client asks you to do anything suspicious, give your lawyer a call. It is better to err on the side of caution than to be named as a defendant in a messy, highly-publicized lawsuit that could result in major liabilities and jeopardize your ability to obtain future work permits and future public contracts in New York City.

Budget Resolution Could Mean Prevailing Wage Requirements for Private Improvements

The New York State Senate's 2018 Budget Resolution includes language that calls for a "discussion about whether the definition of public work should be updated."  It can be construed that this "discussion" opens the door to applying prevailing wage laws to many private construction and improvement projects which were previously not within the definition of public work.

Both houses currently have legislation (S.2975/A.5498) that defines public work so broadly as to encompass construction of private residential buildings, which are assisted only indirectly by government.  This bill bootstraps minimum subsidies for affordable housing as the justification to require the wage regimen applied to public works, which inures to the benefit of construction income.

Covered could be any or all of the following:

1.   Local real property tax abatement or exemption, which is essential for any construction of one and two family homes in the outer boroughs of the City of New York, or most moderate rehabilitation and new apartment renovation or construction. Real property tax abatement programs are used by local governments outside New York City to promote and target first time homebuyers to assist in the purchase of residential housing.  These programs provide assistance to the purchaser, not to the builder/developer.

2.   State agency bonds issued under Federal tax exemption rules, which are used to purchase privately issued bank mortgages on one and two family homes and apartments.  This program is also directed to the purchaser.

3.   Guarantees through SONYMA insurance on State agency bonds which provide credit enhancement to attract private investors in apartment construction or rehabilitation.

Impact of Proposed Steel Tariffs

President Trump announced on Thursday March 1, 2018 that his administration intends to  impose a 25 percent tariff on imported steel and a 10 percent tariff on imported aluminum.  Many details are lacking and official administrative action has not yet been implemented.  Some countries may be exempt so the breadth of the tariffs is not yet known.

The construction industry relies on steel and aluminum and will likely face higher prices.  Price escalation may result in  delays, , a reduced scope,  or projects being cancelled and a force majeure declared or a termination for convenience provision being exercised. Escalation clauses could also impact public projects adversely due to the fact that bidders cannot hold their prices for an extended period of time.

If you don’t have an escalation clause, you may be at  the mercy of the owner to allow a change order for the increased material costs or you may be able to rescind. 

If you’d like to discuss ways to manage this risk please review your agreements and speak with counsel about what steps you should consider.

The Urgency of Filing Liens in Multi-Tier Contracting

Subcontracting is commonplace in the construction industry. The Owner contracts with a General Contractor (GC) who then contracts with one or more subcontractors (Subs) who, in turn, enter into agreements with suppliers and sub-subcontractors (Sub-Subs). While this multi-tiered approach to construction projects is meant to aid in the successful completion of projects by spreading risk and focusing talent, it also has serious implications in terms of the lien rights of the various contractors and subcontractors, especially to those at the lower tiers.

Unlike other areas of the law, the New York Lien Law and the case law interpreting it favors a policy of never forcing anyone to pay twice for the work it contracted to have performed. In order to enforce this policy, the current law provides that a lienor’s rights are derivative of each contracting tier above the lienor. In practice, this means that a lienor cannot recover on its lien if any single one of the following three conditions exist on the project at the time the lien is filed: (1) The Owner owes no funds to the general contractor, (2) the general contractor owes no funds to the subcontractor with whom the lienor contracted, or, (3) most obviously, no funds are owed to the lienor. The Supreme Court of New York, for Queens County, recently released a decision in the case of Trinity Products, LLC v. Carrickmore P&D, LLC1 reaffirming and elaborating on this principle.

Carrickmore was the GC on a project in Queens for demolition of an existing building and construction of a new two-story building on the same lot for approximately $2.6 Million (the “Project”). Carrickmore, in turn, subcontracted with J.J.’s Construction Corp. (“J.J.’s”) for J.J.’s to perform the earthwork, concrete and steel pipe piles work for the Project. J.J.s then created another tier in the contracting process by using various Sub-Subs on the Project, including the plaintiff in the action, Trinity Products, LLC (“Trinity”). For the early part of the Project, everything seemed to be moving along well. However, in the middle of the Project, J.J.’s began to fall behind in performing its work and paying its subcontractors. Eventually, Carrickmore was forced to terminate J.J.’s due to these, and other failures.

At the time Carrickmore terminated J.J.’s, it had already paid J.J.’s over $2 million (based on J.J.’s requisitions). There was still a balance of approximately $600,000.00 on Carrickmore’s contract with J.J.’s; however, J.J.’s had not earned any part of that balance. In fact, after terminating J.J.’s, Carrickmore quickly became aware that J.J.’s previously requisitioned work—for which it had been paid over $2 Million—was incomplete and/or defective in many respects. As Carrickmore still had to fulfill its obligations to the owner, it completed J.J.’s work on its own, utilizing completion subcontractors and suppliers. Carrickmore was able to complete J.J.’s work, although it cost Carrickmore much more than the $600,000 contract balance remaining on its subcontractor with J.J.’s.

After J.J.’s was terminated (and during Carrickmore’s completion of J.J.’s work), Trinity filed a lien based on payments it alleged were due and owing to it from J.J.’s. Carrickmore did not owe any funds to J.J.’s at the time the lien was filed due to back-charges associated with completing and correcting JJ’s work. Near the time that Carrickmore completed J.J.’s work, Trinity, J.J.’s supplier, brought an action to foreclose on the mechanic’s lien in Supreme Court, Queens County.

Carrickmore moved for summary judgment against Trinity, arguing that Trinity could never recover on its mechanic’s lien since Carrickmore could establish that it owed no funds to J.J.’s at the time Trinity filed is mechanic’s lien (and that nothing thereafter became due from Carrickmore to J.J.’s). The Court granted Carrickmore’s motion, reaffirming the caselaw holding that lower tier subcontractors’ rights are derivative of their upstream contractors’ rights. In essence, even though Trinity, the supplier, was owed money by J.J.’s, the subcontractor, it was unable to recover on a mechanic’s lien because J.J.’s had been fully paid by the General Contractor at the time the lien was filed. Trinity’s claim was doomed from the start based on the time it filed its lien. Had Trinity filed its lien earlier—prior to J.J.’s being fully paid—it is possible that Trinity could have recovered on its lien.

TAKEWAY: In multi-tier contracting, lower tier subcontractors and suppliers are best protected by filing a notice of mechanic’s lien as early as possible. This filing will put the upstream parties on notice of the fact that there are payment issues at one or more tiers of the project. It also potentially protects party filing the lien from a defense based upon full payment (payments made after the lien is filed generally do not constitute a defense to a lien claim, while payments made before the lien is filed do generally constitute such a defense). Lienors should also be aware of potential for recovery under payment bonds, which can provide relief to contractors who, for one reason or another, may not have rights under the Lien Law. If in doubt on whether and/or how to file a lien, contractors should contact their construction attorney.


1Trinity v. Carrickmore et. al., Supreme Court of the State of New York, Queens County, Index 708799/2015, Decision dated December 22, 2017.

 

The Insurance Issues Arising from Connecticut’s Crumbling Foundations

Homeowner’s insurance policies are designed to cover many of the “ordinary” perils that a home may face such as fire, theft, a falling tree and the like. However, because not every eventuality can be foreseen, various insurance carriers’ policies are written to account for the “extraordinary” eventualities in different ways. For instance, a building collapse may be excluded by excluding some of its causes, such as “earthquake”, or “earth movement”. A building collapse may also be excluded by reference to its nature; sudden versus gradual. Typically, your average Connecticuter would not have much of a worry about an earthquake-type policy exclusion since your average Nutmeg State earthquake—which is a rare event in and of itself—does nothing more than rattle the knickknack shelf. However, a building can collapse for other reasons, such as substandard construction methods or materials. This is a real worry for those whose homes were constructed of concrete supplied by the JJ Mottes Company in the 1980’s and 90’s.

In the recent case of Metsack v Liberty Mutual Fire Insurance Company and Allstate Insurance Company (2017 WL 706599; 14-CV-01150[VLB]), the United States District Court for the District of Connecticut was confronted with two different insurance policies covering a home with a JJ Mottes foundation. The plaintiffs, the Metsacks, had owed the home since it was constructed in 1992. The Metsacks’ home had been insured by Allstate from the time of its construction through September of 2009, and by Liberty Mutual since. In the years following the construction, the Metsacks noticed minor cracking in the foundation, commencing prior to 2008. Despite these cracks, no problems were perceived with the foundation until April of 2014, when they noticed water infiltrating into the basement. Around that same time, a friend of the Metsacks observed the cracking and suggested that they speak with a contractor. During their conversation with the contractor, the Metsacks first learned that their foundation may be affected by the defective JJ Mottes concrete.

The Metsacks placed claims with both insurance carriers, and the separate experts retained by the Metsacks and the carriers confirmed that the foundation was, indeed, made of defective concrete. The Metsacks’ expert went further and opined that although the house was still safe to live in, the horizontal cracks indicated that the foundation was substantially impaired (which generally occurs between ten and eighteen years after the foundation is poured), and that the foundation walls will continue to weaken until they can no longer support the weight of the home. Both insurance carriers denied the Metsacks’ respective claims, and the Metsacks sued both carriers for coverage under the policies.

Both insurance carriers moved for summary judgment, arguing that the language of their respective policies barred the Metsacks’ claims. The Liberty Mutual policy language provided that the policy covered “direct physical loss … involving collapse of a building or any part of a building caused only by one or more of the following … (b) Hidden decay … or (f) Use of defective material or methods in construction, remodeling or renovation.” The Liberty Mutual policy excluded loss of a foundation, “unless the loss is a direct result of the collapse of a building”, as well as “settling, cracking, shrinking, bulging or expansion”. The Court rejected Liberty Mutual’s argument that the collapse had to effectively result in the building’s crumbling or becoming uninhabitable, finding that case law which provided that the “substantial impairment” of a building “so severe as to materially impair [its] ability to remain upright” sufficed. The Court also brushed back Liberty Mutual’s contentions that the structure at issue was not a foundation, and that the loss occurred outside of the policy period, finding that there were questions of fact as to whether these exceptions applied and that these issues had to be put to a jury. The Allstate policy similarly covered collapses caused by defective methods or materials used in construction. However, unlike the Liberty Mutual policy, the Allstate policy required that any such collapse be “sudden and accidental”. Based on that language, the Court found that Allstate established, as a matter of law, that there could be no circumstances under which the Metsacks’ claims against the Allstate Policy could be viable.

The takeaway from the Metsack case is that a homeowner—or any property owner, contractor, or anyone else covered under an insurance policy—needs to carefully read their policies to see what is, and what is not, covered. If you have any questions about what may be buried deep in your insurance policy, you should reach out to your insurance professional or your attorney.

Be Aware of Sovereign Immunity

When the average person hears the expression “sovereign immunity” they may think of situations where foreign diplomats are immune to civil suits and criminal law because of their “foreign diplomate” status. A wise contractor in the construction industry, however, also knows that throughout the state of New York and other states, sovereign nations exist with whom they may transact business. Whether known as “First Nations”, “Indian Nations” or “Indian Tribes”, doing business with them requires the astute contractor to be aware that he or she is dealing with a sovereign nation, who is not be subject to state judicial dispute resolution proceedings.

Such a situation was faced by Aron Security, Inc. when it performed security service work for the Unkechaug Indian Nation, located in Suffolk County, New York. When the Unkechaug’s failed to pay for the services performed, Aron sued them in the Supreme Court in Suffolk County. Judgement was entered in favor of Aron on May 22, 2014, and Aron served an information subpoena on a member of the Unkechaug’s. The Unkechaug’s made a post-judgment motion to dismiss the action based upon the Supreme Court’s lack of subject matter jurisdiction over the Unkechaug’s who are sovereign Indian Tribe. Aron also made a post-judgment motion to hold the Unkechaug person served with the information subpoena in contempt of court for failing to respond. The Supreme Court denied the Unkechaug’s motion to dismiss and it also denied Aron’s motion for contempt, with leave to renew. Both parties appealed to the Appellate Division, Second Department1.

The Appellate Court reversed and dismissed Aron’s action (including its motion for contempt).

In reaching a determination, the Appellate Court referred to U.S. Supreme Court and other federal court decisions, which held: “[T]hat Indian tribes possess common-law sovereign immunity from suit akin to that enjoyed by other sovereigns is part of this Nation’s long-standing tradition”; that, [T]his immunity extends to ‘suits on contracts, whether those contracts involve governmental or commercial activities and whether they were made on or off a reservation”; that, “[A]lthough a tribe may waive its sovereign immunity, such a waiver, while it need not use the words ‘sovereign immunity’, ‘cannot be implied by must be unequivocally expressed’”; and that, “[W]aivers of immunity are to be strictly construed in favor of the Tribe”.

The Appellate Court also noted (citing U.S. Supreme Court and other federal court cases) that unambiguous arbitration clauses in a contract with a tribe, requiring resolution of all contract-related disputes by arbitration and incorporating arbitration rules and state law for enforcement of arbitration awards in a court of competent jurisdiction, are considered as clear waivers of tribal sovereign immunity.

Aron tried to argue that the Unkechaug’s waived their sovereign immunity because the contract contained a choice-of-law provision that required the contract to be governed by New York law and, that the contract contained a venue provision that required any claim or controversy under the contract to be resolved in Suffolk County and no other jurisdiction.

The Appellate Court rejected Aron’s contentions. As to the contract’s venue provision the court held that the “any claim or controversy” language did not require resolution only by a state court. A party could bring a claim before a mediator, an arbitrator, a tribal court, a state or federal court said the Appellate Court.

With respect to the contract’s New York choice of law provision, the Appellate Court said that New York law could be applied in other forums besides a state of federal court. To the extent this provision is ambiguous, said the Appellate Court, the ambiguity must be resolved against Aron, who drafted the contract, and against waiver of immunity.

Under these circumstances the Unkechaug’s cannot be said to have expressed an unequivocal waiver of sovereign immunity said the Appellate Court.

When doing work for Indian Tribes or other sovereign nations, wise contractors recognize that they are in a situation where the rules of engagement may not be what they are used to operating under. A proposed contract, regardless of who drafted it, should be reviewed by an experienced attorney to provide guidance to the contractor regarding the rules that will have to be followed in the event a dispute arises requiring resolution.


1Aron Security, Inc. v. Unkechaug Indian Nation, 2017 NY Slip Op 04413, (2nd Dept. June 7, 2017)

Drones In Construction – Utility and Risk

In the past few years, we have witnessed fast paced technological development in the area of civilian use of unmanned aircraft systems, commonly referred to as “drones”. While many may be familiar with drones as popular recreational toys, their commercial applications have quickly progressed, reaching all the way to the construction site. This development of drone technology has created new questions of utility and risk for those seeking to reap its benefits. Additionally, as the commercial use of drones has expanded, so too have the regulations relating to the commercial use of drones.

One of the most common current uses of drones, in the construction context, relates to project management and inspections. For instance, a daily morning flyover with one or more drones equipped with cameras could help track progress, as well as accuracy of work being completed. Images taken by the drones can be compared to As-Planned models to determine when and if something has gone right, or wrong, on a project. Drones could also be used to track occurrences on site during working hours and could be helpful in determining the cause of accidents. Drones could also perform flyovers at jobsites during non-working hours to ensure there is no trespassing occurring at the jobsite. All of these functions can be accomplished with basic, lightweight drones, offering large benefits for low costs.

There are many other potential applications for drones that, while currently might be categorized as “space-age”, may not be as far off in the future as they seem. For instance, some large drones currently used in the military are capable of carrying heavy payloads. One could imagine the typical crane being replaced by a host of drones capable of quickly and efficiently transporting project materials directly to difficult-to-reach areas on the jobsite. Project duration, as well as environmental impacts, could potentially be greatly reduced through this technique. At some point, in the perhaps more distant future, drones could be used to fully accomplish certain project tasks, such as delivering and installing modular components, allowing completion of large modular projects at impressive speed. Most mind-boggling of all is the potential for single operators for multiple drones, or wholly unmanned operation of drones. Entire projects could be completed with a fraction of the previously required manpower.

Of course, all of this innovation in the world of drones must be kept in check by government regulation as concerns about safety, privacy, and environmental impact are paramount in our society. As the use of drones becomes more commonplace, there is potential for great benefits in all of these areas. However, as the technology develops, and potential uses are pushed to their limits, government must keep a close eye on the progress to protect the public.

To date, this regulatory role has been assumed by the Federal Aviation Administration (FAA), which enacted regulations meant to strictly govern the use of drones in both commercial and recreational contexts. The basic regulations governing use of drones are codified in the Code of Federal Regulation. (CFR). For the purposes of this article, we will focus solely on the regulations applicable to commercial use of drones in construction, as well as what liability issues are presented by commercial use1.

CFR 47 sets forth registration requirements for aircraft (including drones) and generally requires that any aircraft must be registered with the FAA2. Building on CFR 47, the FAA issued a notice issued in 2007 entitled “Unmanned Aircraft Operation in the National Airspace System”3. This notice required drone operators to obtain an FAA Special Airworthiness Certificate as required for commercial use of any other aircraft. In order to obtain a Special Airworthiness Certificate, an operator is required to submit information to the FAA meant to allow the FAA to ensure safety in the operation of the drone. This information includes: the intended use of the drone; the estimated number of flights the drone will undergo; estimated flight times; and the geographical area over which the drone will be operated. The operator will also be required to submit detailed drawings or photographs of the drone intended for use. Finally, an onsite review of the drone and demonstration of its use may also be required.

Since the 2007 notice, the FAA, due to concerns over time and labor burdens placed on the FAA due to large numbers of applications, issued a December 2015 Notice entitled “Registration and Marking Requirement for Small Unmanned Aircraft”4, which implemented a new registration process for certain drones. The new system allows drones classified as small (weighing less than 55 lbs.), to be registered electronically, for a fee of $5.5 As such, the potential for employing drones of 55 lbs. or less on construction sites have improved greatly.

CFR 107 sets forth numerous operating requirements6 for drones. Some highlights include requirements that:

  1. all operators of drones for commercial purpose must obtain a remote pilot certificate,
  2. a remote pilot in command be designated for any drone flight;
  3. all flights occur during daylight;
  4. an operator may only operator a single drone at any time;
  5. the operator or visual observers must maintain line of sight of the drone at all times;
  6. the drone shall not be flown at a height higher than 400 feet from the ground or, if flown from a structure, within 400 feet of the immediate uppermost limit of the structure; and
  7. operation of the drone cannot interfere with airport traffic and/or operations.

Finally, there are many local city and state ordinances, both pending and enacted, dealing with the operation of drones for private and commercial purposes. The validity and effect of these ordinances are largely unknown as the federal government has already enacted comprehensive (potentially preempting) legislation. Ultimately, it would take a legal challenge to determine the limits of such ordinances. Accordingly, if possible, compliance with them is likely the safest option.

While the potential applications for use of drones are vast, as with most construction related activities, there is risk involved that will likely affect the content of insurance policies contractors using drones will need to obtain. Potential liability in connection with the use of drones in construction generally revolves around privacy and safety concerns. In terms of privacy, drones operate at heights which may allow line of sight to otherwise private areas such as high-rise apartment windows. This privacy violation could be exacerbated by the potential for cyber-attacks, providing unintended parties with access to such lines of sight. Most drones also currently make at least some amount of noise, and in certain cases can be quite loud. Accordingly, construction in residential areas could mean complaints from local constituents about the effects of drones on their ability to enjoy their homes. As for safety, drone use creates potential for serious injuries and/or property damage. For instance, if an operator loses control of a drone due to negligent use or maintenance of a drone or through some manufacturer or product defect, there is potential for a collision with persons, property, or even other aircraft. There is also the potential for drones causing contamination of protected areas through transference of pollutants.

As drones have only recently become more commonplace, and even more so in the commercial context, insurance coverage for the risk associated with their insurance policies is a bit of a grey area. Currently, it appears that the Insurance Services Office Inc. (ISO) general form insurance policies currently exclude coverage for bodily injury and property damage related to use of drones (due to their classification as “aircraft”), with certain exceptions. However, under the generic ISO form, coverage for products liability injuries related to drone usage will likely be covered, as those forms lack an aircraft exclusion. The ISO form also appears to provide some coverage for certain invasions of right to privacy, but generally only to the owner, landlord and/or lessor. There is also apparent coverage for publication of material, for instance, any photos obtained from a drone-related cyber-attack. The ISO recently introduced some additional options for customizing its forms which can affect the risk allocation for drone related injuries by incorporating the use of the term “unmanned aircraft”.7 Until these issues are settled, the takeaway is that contractors, professionals and/or owners intending to use drones for their project must be mindful of contractual insurance requirements and/or risk allocation related to drone operations.

As the uses of drones in construction industry becomes more widespread and technology develops further, there will surely be expansion of federal, state and local legislation that governs their usage, as well as innovations in applicable insurance coverage. Still, regardless of the risks and restrictions, with all of the potential applications currently known and those to be developed in the future, now could be the time for the construction industry to embrace these useful machines. It is important that anyone in the construction industry that intends to utilize the drone technology be prepared to do so safely, and in accordance with federal and local laws.


1 If you would like to learn more about regulation of recreational use, see the D.C. Circuit decision in Taylor v. Huerta, No. 15-1495 (D.C. Cir. 2017) at

2 https://www.ecfr.gov/cgi-bin/text-idx?node=pt14.1.47#se14.1.47_13

3 See 72 Fed. Reg. 6689 (Feb. 13, 2007) at

4 80 Fed. Reg. 78,594 (December 16, 2016)

5 Registration and Marking Requirement for Small Unmanned Aircraft 80 Fed. Reg. 78,594 (December 16, 2015).

6 https://www.ecfr.gov/cgi-bin/text-idx?SID=e331c2fe611df1717386d29eee38b000&mc=true&node=pt14.2.107&rgn=div5#se14.2.107_112

7 Information obtained from Professional Insurance Agents Industry Resource Center. Visit their website at https://pia.org.

How to Comply with the New York City Construction Safety Training Law

On October 16, 2017, Mayor Bill de Blasio signed Local Law 196, formerly known as Intro 1447-C, construction safety training legislation sponsored by New York City Councilmen Jumaane Williams (D-Flatbush) and Carlos Menchaca (D-Sunset Park).

The New York City Building Code now requires that “each permit holder at a building site for which a construction superintendent, site safety manager or site safety coordinator is required” (a “Permit Holder”) is responsible for documenting that their workers have adequately completed the requisite safety training. The way to comply with Local Law 196 is to document that every worker at the building site possesses an appropriate OSHA Site Safety Training (“SST”) Card, and that at least one responsible person at the  job site has an OSHA SST Supervisor Card.       

New Construction Safety Training Mandates for Workers and Supervisors

The safety training mandates of Local Law 196 are going to be phased in gradually over the course of 2018 and 2019. The ordinance was drafted to authorize the New York City Department of Buildings (“DOB”) to have some flexibility in administering rulemaking by establishing a Joint Task Force composed of the DOB Commissioner, representatives from labor unions, unionized contractors, non-union contractors, minority-owned businesses, women-owned businesses, and day laborers. The City Council has delegated authority to the Joint Task Force to determine the content of the safety training, the final safety training hours requirements, and the implementation dates.

If implemented as intended, Local Law 196 mandates will apply to the Permit Holder at every “building site for which a construction superintendent, site safety manager, or site safety coordinator is required” (a “Covered Building Site”). Now construction superintendents are required for all “major construction projects”, including:

  1. new building construction
  2. full demolitions of existing buildings
  3. alterations of over 50% of existing building floor area that requires special structural stability inspection
  4. demolitions of over 50% of an existing building floor
  5. the complete removal of an entire floor
  6. horizontal enlargement
  7. vertical enlargement
  8. any type of work that requires special inspection for support of excavation or underpinning   

The only exception to the 2016 DOB construction superintendent mandate is for 1, 2, and 3 family homes.                                       

In addition, the Local Law 196 construction safety training mandates apply to all Workers at a Covered Building Site. “Workers” include people working in several phases of construction, including renovations, excavation, and demolition. Workers also include all employees of the prime contractor and any subcontractors alike, or anyone acting on behalf of the Permit Holder.

By December 1, 2018 (the “Interim Compliance Date”), Permit Holders will have to ensure that every Worker at every Covered Building Site has completed at least 30 hours of safety training (the “Interim Worker Safety Training Mandate”). An OSHA-30 card will be the standard during an interim period from December 1, 2018 to the Final Compliance Date. During this interim period, a Worker who has completed the OSHA-10 will be able to obtain a temporary card that will allow them to complete the rest of their OSHA-30 while they are working at the Covered Building Site.

By March 1, 2019 (the "Final Compliance Date"), Permit Holders will have to ensure that every Worker at every Covered Building Site has completed at least 40 hours of safety training. By the Final Completion Date, Permit Holders will have to ensure that each Worker has either an OSHA SST card or a temporary OSHA SST card. Limited SST cards will no longer suffice.

In addition to the Safety Training Card Mandate, by December 1, 2018, the Permit Holder will have to comply with the “Superintendent Training Mandate”. The Permit Holder will have to document that at least one person at the job site has a SST supervisor card, specifically every worker who is serving as construction superintendent, or as site safety manager, site safety coordinator, concrete safety manager, or otherwise “a competent person at such site” (the “Superintendent”). 

Recordkeeping and Reporting Mandates for Permit Holders

Keep in mind that the construction safety training mandates do not apply only to individual workers; Local Law 196 establishes recordkeeping and reporting mandates on every Permit Holder for a Covered Building Site.

By March 1, 2018, each Permit Holder must comply with the “Recordkeeping Mandate” by doing the following:

  1. certify that each worker at the job site has complied with the Interim Worker Safety Training Mandate, the Final Work Safety Training Mandate, and/or Superintendent Training Mandate.
  2. maintain a daily log at each job site that identifies each Worker and includes a copy of their respective OSHA safety training card;
  3. upon request by NYC DOB, provide the safety training log for inspection.

It is imperative that the Permit Holder for every Covered Building Site strictly comply with the Recordkeeping Mandate. Even if everyone working at the Covered Building Site has complied with the training mandates, a Permit Holder found to be lacking proper logs for a given work day is presumed to be noncompliant.

Consequences for Non-Compliance with Local Law 196

Denial of DOB Permits        

Going forward, NYC DOB will make granting permits for construction and demolition work conditional on the permit applicant’s compliance with Local Law 196. If the applicant for construction or demolition work does not certify that all of the workers will be compliant with the Local Law 196 construction safety training mandates, DOB will deny  permits.  

Violations for Worker’s Failure to Complete Safety Training

If the NYC DOB Commissioner determines “that a worker at a building site is not in compliance” with any of the new training mandates, the Commissioner will issue a notice of violation to the Permit Holder, the non-compliant worker’s Employer (if the Employer is different from the Permit Holder), and the Owner of the job site. Even if they are separate entities, DOB can charge each of the Permit Holder, Employer, and Owner with separate violations and issue separate civil penalties.  

In the event that DOB determines that a Permit Holder is in violation of Local Law 196, the Permit Holder will have to pay for the costs of the Worker to obtain the required safety training or “otherwise arrange” for the Worker to receive the safety training at no cost to the non-compliant Worker. The non-compliant Worker will have to remain employed at the Building Site under the same terms and conditions, and must be paid as though he or she were working at the job site 40 hours each week at the same wage.

Violations for Failure to Maintain the Daily Compliance Log

If a Permit Holder at a Covered Building Site has not maintained a daily log recording the names of each Worker at the site and each Worker’s respective safety training cards, that is a per se violation of Local Law 196.  If DOB determines that a Permit Holder failed to maintain a log, it establishes a rebuttable presumption that each Worker for whom the Permit Holder is responsible for ensuring compliance “is not compliant”, and it will result in notices of violation for each unrecorded day worked by each Worker. 

Civil Penalties

For “lesser violations” of Local Law 196, DOB can impose a penalty up to $500 for each violation. For “major violations”, DOB can impose a penalty up to $10,000 for each violation. To boot, DOB can impose an additional penalty of up to $250 for each month that the “major violation” is not corrected. For “immediately hazardous violations”, DOB can impose a civil penalty up to $25,000 for each violation. DOB can also impose an additional penalty up to $1,000 for each day that the “immediately hazardous violation” is not corrected.

At present, the statute is unclear as to what precisely constitutes a “lesser violation” versus a “major violation” or an “immediately hazardous violation” of Local Law 196, and it appears that DOB will have wide discretion in meting out civil penalties.             

In Practice    

If you have reason to believe that any members of your work force are lacking an OSHA-30 card, it would be wise to start planning for the Interim Compliance Date which will most likely come into effect on December 1, 2018. Also, do not forget that your superintendent, safety supervisor, or another “competent person” will have to comply with the Superintendent Training Mandate by December 1, 2018 as well.

By May 1, 2019, however, all of your Workers are going to need to have 40 hours of safety training.  Instead of doing it piecemeal, it might be more effective to make sure that your work force undergoes all of their construction safety training at once to comply with the mandate for the Final Compliance Date.

Remember that if you are the Permit Holder for a Covered Building Site, you are responsible for not only your own employees, but also for every one of your subcontractor’s compliance with the safety training mandates. Do not expose yourself to risk by hiring subcontractors whom you know are lacking their OSHA cards.

Getting Paid for Your Extra Work

Most construction contracts with an agreed upon base price will provide for adjustment of the schedule and price if the contractor performs work that is additional to the scope originally agreed upon. Such adjustments, which are often crucial to the contractor making a profit on a job, typically place notice requirements on the contractor, especially on public projects. The contractor’s failure to precisely follow these notice requirements, which can be burdensome in terms of time requirements and substance, can be fatal to the contractor’s extra work claim.

The importance of following contractual notice requirements for extra work is highlighted by a recent decision of The New York Appellate Division, Third Department, in the case of Ridley Electric Company, Inc. v. DASNY1 Ridley entered into a contract with the Dormitory Authority of the State of New York (“DASNY”) to be the prime contractor on a New York State public project for construction of the New York State Veteran’s Home (the “Project”). During Ridley’s performance of its work, issues arose relating to the design of the Project ceiling, causing DASNY to make various adjustments on the Project so Ridley could complete its work. Ridley substantially completed its contract work, including work Ridley considered extra, by September of 2008. In March of 2009, Ridley requested payment for the alleged extra work it performed relating not only to the ceiling issue, but also to cleanup work it performed. In February of 2010, DASNY responded to Ridley’s request, agreeing Ridley was due compensation for certain extra work, but solely relating to the ceiling issue. DASNY also provided proposed change orders for the extra work relating to the ceiling issue. Ridley refused to execute DASNY’s proposed change orders because of pricing issues, and it set forth proposed change orders of its own. DASNY refused to execute the change orders proposed by Ridley.

Based on this disagreement, Ridley sued DASNY in Supreme Court for breach of contract seeking its contract balance and delay damages. DASNY asserted a defense based on Ridley’s failure to follow the contractual notice requirements. The contract between Ridley and DASNY provided that DASNY could order Ridley to perform extra work and would use change orders to adjust the contract price accordingly. It also provided that if Ridley believed it was ordered to perform work that was extra, Ridley had to notify DASNY of this claim in writing within 15 days of being ordered to perform allegedly extra work, and follow up by submitting an estimate of anticipated cost within 30 days. The contract further provided that Ridley’s failure to comply with these requirements would constitute “a conclusive and binding determination on the part of the contractor that the work in question does not involve extra work…and, also, a waiver… of all claims for additional compensation or damages as a result of the work.”. During motion practice, Supreme Court found that Ridley had failed to follow the extra work notice and reporting requirements, and it dismissed Ridley’s complaint.

Ridley appealed to the Appellate Division, Third Department. Ridley conceded that it did not comply with the contractual extra work notice and reporting requirements, but argued that the Supreme Court erred in dismissing its complaint as DASNY: (1) knew Ridley was performing extra work; and (2) waived its defense of the notice requirements by acknowledging Ridley was entitled to extra compensation in its March 2009 correspondence. The Third Department affirmed the Supreme Court, citing Ridley’s failure to comply with the notice requirement by making its claims in March of 2009, long after the notice period in the contract expired. The Court also specified the importance of notice requirements in keeping owners aware of budget updates, especially on public projects where there is an important interest in avoiding the waste of public funds. Based on this important interest, the Third Department required that the notice requirements “must be literally performed”, dooming Ridley’s claim to extra compensation in connection with both the ceiling and clean up work.

Importantly, the Court found that even though DASNY had admitted that it was aware of Ridley’s entitlement to compensation for extra work related to the ceiling issue, without proper notice of its extra work claim being made, Ridley had no viable claim. It also rejected Ridley’s point that the March 2009 letter constituted a waiver of the extra work notice requirement. In doing so, the Court noted a waiver can only be accomplished through an “explicit, unmistakable and unambiguous” act. It also pointed to contract provisions which provided that certain actions by DASNY, such as ordering extra work, issuing change orders, and making partial payments could not be construed as waivers of contract terms.

TAKEWAY: Contractors can often end up in contracts that place onerous requirements on the contractor in connection with claims for extra work. These provisions are enforceable limitations on the rights of the contractor, and are strictly enforced especially, on public projects. Accordingly, it is important that contractors note what notice requirements exist for extra work claims (and other contingencies) when negotiating contracts, and must remain aware of these requirements during performance of the work. If in doubt, contact your construction attorney to help you preserve your claims.

1 Ridley Elec. Co., Inc. v Dormitory Auth. of State, 152 AD3d 1129 [3d Dept 2017]

 

 

Contractor’s Lien Waiver Does Not Bar Claim For Unpaid Work

A waiver of lien can serve as an effective tool to bar unanticipated claims for unpaid/extra work on a project. Although Courts will generally enforce an executed lien waiver as a bar to such claims, that is not always the case. In Shamrock Materials LLC v. Impact Environmental Engineering, PLLC (149 A.D.3d 1001 [2d Dept 2017]), the Appellate Division, Second Department, addressed the issue of the enforceability of a lien waiver.

The dispute in Shamrock Materials LLC arises out of a 2009-2010 project to lengthen and widen the Bay Runway at John F. Kennedy International Airport (“Project”). Tutor Perini served as the general contractor who subcontracted work to defendant, Impact Environmental Engineering. Impact Environmental Engineering, in turn, entered into a subcontract with the plaintiff, Shamrock Materials, for the removal and disposal of about 240,000 cubic yards of excavated materials. The price for Shamrock’s work was an allegedly agreed upon unit price, which was dependent on the type of material, screening needs and method of transport. Shamrock Materials claimed that it was still due and owing at least $458,450.75 in connection with the Project. Impact Environmental claimed, among other things, that during the course of the Project Shamrock Materials executed lien waivers waiving such claims, and that Impact Environmental had actually overpaid and, as a result, was owed a credit of $57,178.96.

Shamrock Materials filed a breach of contract lawsuit, which proceeded to trial. Initially, Impact Environmental moved for judgment as a matter of law, contending that Shamrock Materials had waived its claim based on a series of executed lien waivers. The Court denied this motion and permitted the jury to determine the parties’ intention as to the effect of the lien waiver documents. At trial, the jury returned a verdict in favor of Shamrock Materials in the total amount of $547,278.61, plus interests and costs.  

The Appellate Division upheld the lower court’s decision, finding that “the evidence at trial failed to establish, as a matter of law, that the plaintiff waived its claim to recover” the unpaid amounts. In its decision, the Appellate Division cited Penava Mech. Corp. v Afgo Mech. Servs., Inc. (71 AD3d 493, 495 [1st Dept 2010]). In Penava, it was held that the parties’ course of conduct was such that the subcontractor was required to sign waivers whenever it received payments, and that “the parties treated the waivers as mere receipts of the amounts stated in the waivers, not as complete waivers of all claims to that point”.

It should be noted that courts will generally enforce waiver and release documents to the extent that they are a true reflection of the intent of the parties. If there is evidence that the parties course of dealing is inconsistent with the terms of the release document, a court may decline to enforce the waiver and release against the contractor. Here, Shamrock was ultimately able to recover for unpaid work, but this result is more the exception than the rule. All too often contractors fail to carefully read waiver and release documents in the hope of receiving faster progress payments (and end up paying a substantial price for this oversight). The more prudent course of action is to carve out an exception to any waiver and release documents they sign when there is an outstanding balance or it is contemplated that additional work is to be performed at the time that the lien waiver is signed.