Court Permits Oral Guarantee Claim To Proceed After Bankruptcy Of Owner

It is not unusual of that an owner, or an upstream contractor, encounters financial difficulties during a project which jeopardize—or completely stop—the contractor’s payments. However, in today’s modern world, the owner may be but a cog in a larger wheel, with ramifications suffered by others who are somehow related to, or set to benefit from, the construction (such as lenders, parent entities, and others). In such instances, in order to salvage the benefits of the construction, those related to the owner may agree to pay the contractor to finish its work in place of the owner, or even pay the contractor for the previous, unpaid work. An appellate court, in the recent case of Villnave Construction Services, Inc. v Crossgates Mall General Company Newco, LLC, reminds us that such agreements must generally be in writing, and that the exceptions to that general rule are narrow.

Background

In 2016, defendant Albany MIB+K, LLC leased a space at the Crossgates Mall with the intention to operate a franchise of Waxy’s Modern Irish Bar and Kitchen. In March of 2017, defendant Waxy O’Connor’s Management Company, the franchisor and representative of the Waxy’s brand, worked with MIB+K to negotiate a construction agreement with defendant Trinity Building and Construction Management Corp., for the construction, and to ensure that the buildout would be consistent with other Waxy’s locations.
After construction commenced, MIB+K began to fall behind on payments. In order to have the construction continue, Waxy O’Connor’s Management Co., and defendants Ashok Patel, Amisha II, LLC, and Jasmine Hotel Management (the group of which were all somehow related to Waxy O’Connor’s), and defendant Crossgates Mall Devco, LLC (the Mall), promised to pay Trinity if Trinity would continue the construction. Shortly thereafter, when MIB+K filed a bankruptcy petition, Trinity’s principal reached out to the Waxy’s Group and the Mall to ascertain their intentions. The Waxy’s Group and the Mall responded by orally committing to pay Trinity for its continued performance, so long as Trinity would not suspend its work under the contract (as was its contractual right) based on MIB+K’s failure to pay. Based on these oral promises, Trinity continued to perform under the contract. However, Trinity only received a partial payment from one of the Waxy’s Group.
Ultimately, when MIB+K’s lease was terminated based on the non-payment of rent, one of Trinity’s unpaid subcontractors filed, and sued to foreclose, a mechanic’s lien. Trinity cross-claimed against the Waxy’s Group and the Mall to recover on the oral promises of payment, specifically asserting claims for unjust enrichment, promissory estoppel, and breach of the guarantee. The Waxy’s Group and Mall defendants moved to dismiss, arguing that the unjust enrichment claim failed in light of the express written contract between Trinity and MIB+K, and that the alleged guarantee promises were not enforceable as they were not in writing.

Decision

First, as to the unjust enrichment claim (and as this column has repeatedly noted), under controlling case law, such claims generally fail in the presence of an enforceable written contract covering the subject of the unjust enrichment claim. However, because of MIB+K’s bankruptcy filing, the enforceability of that contract was called into legal question (since the bankruptcy court has the authority to discharge the contract). Accordingly, the court held that the unjust enrichment claim could be asserted as an alternate to what may be an unenforceable, discharged contract.
Turning to the oral promises, the court also correctly noted (as this column similarly noted in our October, 2020 issue) that generally, such promises have to be in writing in order to be enforceable. However, here, unlike in the case referenced in the previous column, Trinity alleged that it entered into an agreement to not only perform under the old contract with MIB+K, but it also agreed to refrain from terminating its contract with MIB+K—even though it had the legal right to do so. This delay in terminating its performance under the contract benefitted the Waxy’s Group and Mall defendants by permitting them time to avoid their own personal obligations under the defaulted MIB+K lease. Given these allegations of new consideration—separate and apart from those obligations that Trinity was already under—and the new benefits to be realized by the promisors, the narrow exception to the Statute of Frauds (a law requiring certain agreements to be in writing) could apply, and the claim was permitted to proceed to discovery on this issue.

Comment

It is always comforting for a contractor, when faced with financial difficulties of an owner or an upstream contractor, to find solace in another’s promise to pay. However, such oral promises are generally unenforceable unless they fit into a narrow exception. Accordingly, the gold standard, of course, is to get such promises in writing. Failing that, you should consult with experienced construction counsel so that you can take actions, similar to those referenced by the court here, which will permit you to allege, and ultimately show, that the promise to pay is supported by new, additional consideration (such as not exercising a right you would otherwise have exercised under the contract), and the new promise benefits the promisors directly in some way. Essentially, you are making a new contract, so be prepared to treat (and document) it as such. After all, and as we have often cautioned: if it ain’t in writing, it didn’t happen!

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Court Enforces Whistleblower Protection Statute In Face Of Contract Permitting Owner To Direct Discharge Of Contractor’s Employee

While this column often deals with issues relating to the construction industry, it is sometimes overlooked that construction contractors are, more generally, employers, just like those outside the construction industry. Those generally applicable rules, however, can be just as easy to run afoul as those which are uniquely applicable to the construction industry. In the recent case of Shevlin v Wonder Works Construction & Development Corp., a Court reminds us that New York’s generally applicable whistleblower protection statute (Labor Law §740) is also applicable to construction contractors.

Background

Prior to 2013, Wonder Works Construction Corp. entered into a contract with 421 Kent Development, LLC for Wonder Works to be the construction manager for a construction project at 421 Kent Avenue in Brooklyn. The contract between Wonder Works and 421 Kent provided that “[421 Kent] reserves the right to direct the removal of any of [Wonder Works’] staff for cause (at [421 Kent’s] sole discretion) including Key Personnel, and [Wonder Works] shall promptly replace such individuals with competent substitutes acceptable to [421 Kent]”. 

In 2013, Scott Shevlin was hired by Wonder Works to be a site superintendent at the 421 Kent Avenue project. At the commencement of the project, the 421 Kent Avenue site was surrounded by a fence around three sides, which had been left by the previous owner. The site was divided by a private street, which was guarded by rolling gates that were supposed to have been closed when not in use. The New York City Department of Buildings required that Wonder Works both build an interior fence on the fourth side of the site, and keep the rolling gates closed when not in use, in order to safeguard the site as a condition of lifting a previous stop-work order. If the gates were left open, the public would use the private street as a shortcut between two local thoroughfares.

A problem arose with the site’s neighbor, who preferred to leave the rolling gates open for his own convenience. As DOB continued to warn Wonder Works about leaving the gates open, Shevlin would close them. Both Wonder Works’ vice president and 421 Kent Development’s site representative would tell Shevlin he should leave the gates well enough alone, and that they did not care about whether the gates were open or closed. This indifference was communicated to Shevlin several more times prior to his termination, and Shevlin, pursuant to both DOB’s and his immediate supervisor’s instructions, would insist on keeping the gates closed. 

In January of 2014, Wonder Works received a letter from 421 Kent Development’s site representative directing Wonder Works to replace Shevlin with “alternative competent personnel for cause”, claiming that “Shevlin has demonstrated a lack of fiduciary responsibility and a retaliatory approach in dealing with daily issues”. In response, Wonder Works terminated Shevlin’s employment. In subsequent correspondence between Shevlin and another Wonder Works principal, Shevlin was advised that the termination was the owner’s decision, and that Shevlin did nothing wrong.

Shevlin commenced a lawsuit under New York’s Whistleblower Protection Statute, Section 740 of the Labor Law, against both Wonder Works and 421 Kent Development, alleging that he was terminated for insisting on keeping the gates closed, even though it caused consternation with the neighbor. Wonder Works and 421 Kent Development both claimed that the termination had nothing to do with the rolling gates issue. Wonder Works also claimed that in light of its contract with 421 Kent Development, it was required to terminate Shevlin and had no discretion in the matter; 421 Kent Development also claimed that it could not be held liable because it was not Shevlin’s employer.

Decision

A non-jury trial was held on Shevlin’s claim, and the court credited the testimony that there were no complaints about Shevlin’s employment other than his insistence on keeping the gates closed, and discredited the testimony that his firing was unrelated to the access issue. In order to find a violation of the version of Section 740 in effect at the time, the court also had to find that there was, in fact a violation of a statute, code, etc. The court found such a violation of Section 3307.3.4 of the Building Code, which requires that openings in fences, sidewalk sheds, barriers, and railings be closed at all times except during actual loading and unloading operations, and the court linked Shevlin’s termination to his insistence on keeping these gates closed. (The current version of the statute only requires that the employee have a reasonable belief about the violation of a statute, code, etc., not that the violation actually exist). 

The court found that Wonder Works’ defense of just following the contract was unconvincing, holding that while the contract did give 421 Kent Development the right to remove Wonder Works’ employees “for cause”, as determined to exist in the sole determination of 421 Kent Development, it could not require Wonder Works to violate applicable law in doing so. As to 421 Kent Development, even though it was the root cause of Shevlin’s termination, it was not liable because the statute was specifically made applicable to employers, and 421 Kent Development was not Shevlin’s employer. Based on these findings, the court dismissed the case against 421 Kent Development, and it directed Wonder Works to pay Shevlin $227,000 in back pay, plus his attorney’s fees.

Comment

In dealing with contractual provisions between parties, this column has routinely cautioned that obligations should be made consistent both upstream and downstream (e.g.: if a GC’s contract with the owner requires arbitration, the GC should require arbitration of its subcontractors). As the Shevlin court reminds us, those obligations must also be consistent with state law, including generally applicable employment law. As Wonder Works learned here, the defense of “just following the contract” was not sufficient to save it from a significant lost wages claim—plus potentially over $50,000 in attorney’s fees.

About the author: Thomas H. Welby, an attorney and licensed professional engineer, is General Counsel to the Construction Industry Council of Westchester and the Hudson Valley, and is the Founder of, and Senior Counsel to the law firm of Welby, Brady & Greenblatt, LLP, with offices located throughout the Tri-State/Greater Metropolitan Region. Gregory J. Spaun, General Counsel to the Queens and Bronx Building Association, and an attorney and a partner with the firm, co-authors this series with Mr. Welby.

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Appellate Court Enforces Waiver Of Consequential Damages

References to consequential damages are often found in construction contracts, without appropriate appreciation as to what, exactly, those damages are. These references are most often found in mutual waivers of such damages; but the question is begged as to what, exactly, is being waived. In the recent case of Lam Platt Street Hotel LLC v Golden Pearl Construction LLC, an appellate court reminds us that waivers of consequential damages are strictly enforced. Accordingly, contractors would be well advised to appreciate the full import of such clauses.

Background

In 2011, Lam Platt Street Hotel LLC entered into an agreement to construct a hotel near the South Street Seaport, and Golden Pearl Construction was retained as the general contractor. The form of contract was an AIA A101/201 combination, which contained a time of the essence clause requiring completion before Super Bowl XLVII, which was held in February of 2014 in (as much as the “New York” football teams eschew the name) nearby East Rutherford, New Jersey. The contract also contained provisions governing termination for cause, which required certification by the project’s architect that the general contractor was in default (and which would also permit Lam Platt to suspend its obligation to make further payments to Golden Pearl until the completion of the project), and for convenience (which required that Lam Platt pay Golden Pearl for all work completed through the termination date). Finally, the contract contained a mutual waiver of consequential damages, which expressly included “rental expenses, loss of use, income, profit, revenue, financing, business and reputation”. 

During construction, disputes arose between Lam Platt and Golden Pearl over extra work and payments, and Golden Pearl’s alleged failure to properly staff the project. In December of 2014, Lam Platt and Golden Pearl ostensibly resolved their differences, and the project’s time and price were increased. Unfortunately, this agreement was not the last word on these subjects, and the relationship broke down. In June of 2015, Lam Platt terminated Golden Pearl’s contract, without specifying whether the termination was for cause or for convenience, but also without any certification by the architect. Because there was no architect’s certification, Golden Pearl rejected any claim that the termination was for cause. (Ultimately, the architect refused to certify that the termination was for cause, citing its own contract and claiming that it had no such responsibility to do so.) Golden Pearl subsequently filed a mechanic’s lien against the property, claiming that it was owed nearly $3.2 million.

In February of 2017, Lam Platt sued Golden Pearl for breach of contract, seeking, amongst other damages, delay costs and the profits it would have realized if the project had been completed in time for the Super Bowl. Golden Pearl moved to dismiss this claim, arguing that the damages that Lam Platt sought were specifically barred by the waiver of consequential damages contained in the contract. 

Decision

The motion court granted Golden Pearl’s motion, and the appellate court affirmed. In doing so, both courts cited to well settled case law that an agreement between the parties to allocate the risk of loss via a waiver of consequential damages must be enforced as written.

Comment

As the courts here noted, a waiver of consequential damages is, essentially, an agreement as to how the risk of a breach is to be allocated. To best understand that risk, one must understand what “consequential damages” really are: damages which flow indirectly from the breach (as a consequence of that breach), rather than those which are caused directly by the breach. Unfortunately, this language is not often clear to attorneys, and is frequently the subject of endless argument and court ruling. The best way to illustrate the difference is by example: direct damages often include the cost to repair defective work, the cost to complete incomplete work, the payment owed under the contract, the loss of value of a project as a result of improper work, and the profit the contractor would have received if it had been permitted to complete the job and not improperly terminated; consequential damages, on the other hand, often include lost profits from the intended use of the project, lost rents, or lost profits on jobs not taken because the contractor was tied up on the disputed project (to be contrasted from lost profits on the revenues not realized because of an improper termination, which are considered direct damages), extended overhead and delay costs, increased financing costs, and even lost bonding capacity. Because these items can vary widely—and are often difficult to prove—parties frequently include a liquidated damages provision, as an estimate of damages, along with the waiver of consequential damages. To better understand what would be included and excluded from recovery on any particular project under the applicable contract, contractors would be well advised to consult with experienced construction counsel so that they can fully understand how they are allocating the risks of a breach of the contract they are about to enter.

Parenthetically, it must also be noted that a significant issue in Lam Platt was whether the termination was one for cause or convenience. Crucially, under the contract at issue, no termination could be made for cause without the actions of a third-party to the contract—here, the architect—certifying that the general contractor was in default. The architect declined to issue any such certification because his own contract did not require him to do so. This dichotomy shows the importance of harmonizing all upstream, downstream, and parallel contracts for the consistency of obligations, and making sure that if one contract provides that a third-party is to act as a condition precedent to any action by the contracting party, that such third-party is actually under his or her own obligation to do so.

About the author: Thomas H. Welby, an attorney and licensed professional engineer, is General Counsel to the Construction Industry Council of Westchester and the Hudson Valley, and is the Founder of, and Senior Counsel to the law firm of Welby, Brady & Greenblatt, LLP, with offices located throughout the Tri-State/Greater Metropolitan Region. Gregory J. Spaun, General Counsel to the Queens and Bronx Building Association, and an attorney and a partner with the firm, co-authors this series with Mr. Welby. 

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Court Reminds Contractors That Cure Periods Are Ignored At Their Own Peril

It is well known that in business, including the construction business, the applicable contract governs the relationship between the parties. As the subject of negotiation, its specific terms should be familiar to all parties. Unfortunately, during the bustle of the project, some contractual provisions, including notice provisions and right to cure provisions, fall by the wayside. While, the majority of the time, these missed provisions end up being inconsequential (because the parties make their way past the issues and deal with them at the end of the job), an appellate court, in East Empire Construction, Inc. v Borough Construction Group LLC, reminds us of the importance of complying with these provisions so that any subsequent actions, such as a termination, will be valid.

Background

In 2015, Borough Construction Group, a general contractor, entered into a subcontract with East Empire Construction whereby East Empire was to perform the steel scope of work for the construction of a building in Columbus Circle in Manhattan. The relevant contract, which was an AIA A401/201 form of contract, contained a provision permitting Borough to undertake to correct East Empire’s defective work if East Empire failed to do so itself within five days of receiving notice of such defective work. Another provision of the contract required Borough to provide East Empire with a 10 day period within which to cure any defect as a condition precedent to termination.
In May of 2016, Borough sent East Empire a notice of termination, stating that the subcontract would be terminated three days from the date of the letter, claiming that East Empire was in default by “failing to provide sufficient manpower [] [and] failing to meet the schedule, safety regulations and qualified workmanship” for the project. The parties discussed these issues and, after negotiations, Borough withdrew its termination letter. One week later, Borough sent East Empire an identical notice of termination, and subsequently retained a new steel contractor to complete East Empire’s scope of work.
In November of 2016, East Empire sued Borough for breach of contract, alleging that Borough breached the contract by improperly terminating East Empire’s subcontract, and seeking the monies for which it had invoiced up until the termination. Borough denied the allegations in the complaint, and asserted East Empire’s claimed breaches of the subcontract as a defense to payment. East Empire moved for summary judgment in its favor on its breach of contract claim, and dismissing Borough’s affirmative defense, on the grounds that Borough denied it of its contractual opportunity to cure the claimed defects. In opposition, Borough argued that East Empire’s acts of default were persistent and incurable. 

Decision

The motion court granted East Empire’s motion, and found that by failing to give East Empire the opportunity to cure provided for in the subcontract, Borough’s second attempt at termination was improper and, itself, constituted a breach of that contract. The appellate court affirmed, addressing not only the clear lack of the contractually required cure period, but also the limited exceptions to this requirement. The appellate court discussed that while such a notice to cure need not be given where: the terminated party repudiates its performance; the terminated party abandons the project; the breach is impossible to cure; or the breach is so substantial that it undermines the entire contractual relationship such that it cannot be cured, the exceptions are of very limited scope, and none applied here. In doing so, the appellate court cited well settled law in holding that the defaults complained of, mere faulty steelwork and failing to meet the schedule, was “the very situation to which the cure provision was intended to apply”. 

Comment

Notice and opportunity to cure provisions, like other contractual provisions, must—absent extraordinary circumstances—be strictly complied with. Typically, arguments that extraordinary circumstances apply are made not when there are such extraordinary circumstances, but when the notice and cure provisions are overlooked (or, in a haste to remove a contractor from a project, simply not complied with). East Empire highlights how a subcontractor in default was able to completely turn the tables on the general contractor and not only avoid the consequences of its own default (being backcharged for the excess cost incurred by the general contractor to complete its work), but also have an affirmative recovery and get paid for its (claimed defective) work. While the reflexive statement to a contractor in default is to “get off of my jobsite”, contractors would be well advised to review their contracts to see if there are notice and cure provisions, and strictly comply with them. Surely, the offense at having the contractor around for an extra few days while he tries to remedy a default is not as grievous as having to not only forego a backcharge for excess completion costs, but also actually writing that contractor a check for work you believe is defective. If you have any questions as to whether such an exception applies, experienced construction counsel can help.

About the author: Thomas H. Welby, an attorney and licensed professional engineer, is General Counsel to the Construction Industry Council of Westchester and the Hudson Valley, and is the Founder of, and Senior Counsel to the law firm of Welby, Brady & Greenblatt, LLP, with offices located throughout the Tri-State/Greater Metropolitan Region. Gregory J. Spaun, General Counsel to the Queens and Bronx Building Association, and an attorney and a partner with the firm, co-authors this series with Mr. Welby.

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Court Reinforces that Arbitration Must be Consensual

Arbitration is often the most prompt and just means for dispute resolution. However, this leads to the questions: when can you arbitrate? and: what arbitration remedies might a contractor choose to exercise?

In BML Properties Ltd. v. China Construction America, Inc., et al., an appellate court reminded us that arbitration is a consensual process. BML involved a series of agreements in connection with the development of the multi-billion Baha Mar resort complex in the Bahamas. BML was the direct parent of Baha Mar Ltd.  In 2009, Baha Mar Ltd. and one of the China Construction defendants memorialized their agreement in a Main Construction Contract, which provided that any suit, action, or proceedings shall be brought in the courts of the State of New York, or the United States District Court, located in the Borough of Manhattan in the City of New York. A subsequent Bahamian receivership proceeding (think: bankruptcy) resulted in the sale of the assets of Baha Mar Ltd. to Perfect Luck Assets Ltd, (“Perfect Luck”). Consequently, BML lost its entire investment in in Baha Mar Ltd., or approximately $845 million, as well as its expected profits from the resort.

In 2016, Perfect Luck and one of the China Construction defendants amended the Main Construction Contract, deleting the New York forum selection clause and inserting a new provision requiring that any disputes be referred to and finally resolved by arbitration under the Rules of the International Chamber of Commerce. On December 26, 2017, BML filed a lawsuit in New York State Supreme Court in Manhattan alleging a multi-year scheme to fraudulently delay the Baha Mar resort project and increase construction costs. China Construction moved pursuant to NY CPLR 7503 and to the Federal Arbitration Act to compel arbitration.  BML countered, arguing that BML had not consented to arbitration and, accordingly, could not be compelled to participate. Correctly, the Court determined that its threshold question was whether the parties made a valid agreement to arbitrate, noting that the proponent of arbitration has the burden of demonstrating that the parties agreed to arbitrate. The appellate court affirmed, noting that while the Federal Arbitration Act favors arbitration, it is limited by the principle that arbitration is always a matter of consent, not coercion.  Defendants, while moving to compel arbitration, argued that the Main Construction Contract, as amended by Amendment No. 9, required BML to arbitrate the dispute.  However, BML was a non-signatory to Amendment No. 9, which post-dates the disputes at issue.

While in certain limited circumstances New York courts can impute the intent to arbitrate to a non-signatory, such as where the non-signatory may evince an intent to be bound or where the non-signatory received a direct benefit from a contract containing an arbitration clause, such as payment under the contract, or enforcement of the contract against others.  However, neither the lower nor the appellate courts found those triggering circumstances here. Accordingly, it found the arbitration clause inapplicable and, therefore, denied the motion to compel.

To understand the lower court’s ruling, it is important to remember the basic premise of arbitration: that arbitration is a consensual method of dispute resolution.  Parties contemplating arbitration can enter into an arbitration agreement either before or after a dispute arises; but enter into an agreement they must. The situation in BML fatally departed from this basic requirement and, accordingly, the case was relegated to ordinary litigation.

CONCLUSION:

It is clear that Courts are more inclined to sustain the right to arbitrate when supported by signed documentation, rather than surrounding factual circumstances. Should you believe you have a right to arbitrate, it is best to have the documents or circumstances on which you rely reviewed by your attorneys.

Court Dismisses Delay Claim Against Non-party To Contract

In this column, we have often addressed delay claims—typically in the context of when, if ever, a contractor can assert such a claim in the face of a no-damages-for-delay clause. However, the recent case of Dworkin Construction Corp. v Consolidated Edison Co. of NY, an appellate court reminds us that fundamentally, delay claims are creatures of contract and, therefore, a contract between both the proponent and the target of the delay claim is absolutely necessary to proceed.

Background

Dworkin Construction Corp. was retained by Lush Cosmetics, a makeup retailer and lessee of a property on East 14th Street in Manhattan, to renovate a commercial space and build out a store that would suit Lush’s particular needs. Lush’s needs included the installation of an additional electrical shunt to supply more power for the store. As a part and parcel of this scope of work, Dworkin applied to Con Ed for required approvals, to which Con Ed responded very slowly, resulting in a delay of the completion of the project. As a result of this delay, Dworkin incurred $82,805 in damages—and lost Lush’s business.

Dworkin sued Con Ed for negligence and breach of contract to recover the out of pocket expenses, as well as the claimed $1,068,405 in lost profits resulting from its loss of Lush’s business. In its complaint, it alleged that Con Ed was negligent by failing to exercise reasonable care in the processing of Dworkin’s application. Dworkin, alternatively, alleged that it entered into a contract with Con Ed for Con Ed to reasonably and diligently process its application for the service upgrade, and that Con Ed breached the contract by failing to do so. Con Ed moved to dismiss the lawsuit.

Decision

The motion court granted Con Ed’s motion, holding that even if Con Ed took an extraordinarily long time to process the application, Dworkin could not assert such a claim in the absence of a contract. Dworkin appealed, and the appellate court affirmed. As to the negligence claim, the appellate court held that in addition to Con Ed not having any common-law duty to Dworkin, the negligence claim failed because it sought only economic damages—which, under well settled case law, are limited to breach of contract claims. As to that breach of contract claim, the appellate court found that even though Con Ed provided invoices and a “service determination” listing Dworkin as the customer, Dworkin was not doing the work for its own service but, rather, that of its customer, Lush, for which it was acting as agent. Further, and specifically as to Con Ed, the appellate court also referenced its tariff (its operating authority granted by the Public Service Commission), under which Con Ed has the obligation to provide utility services to all customers equally, and held that Con Ed does not have the legal authority to enter into any agreement which guarantees service within a particular time frame.

Comment

Dealing with utilities can be as frustrating, and bureaucratic, as dealing with government agencies themselves. On top of this, the frustration of delays (and their financial impact on a project) only adds to the madness—particularly when they are not caused through any fault of the contractor (or the subcontractors working under it). However, because the damages relating to a delay are purely economic, courts require an existing contractual relationship between the parties which deals with the issue—which is usually either in the form of setting deadlines with a time of the essence clause (thus putting parties on notice that there could be the assessment of damages if that crucial date passes), or a liquidated damages clause which specifies damages to be awarded in the case of a delay, or a no-damages-for-delay clause. In the absence of such a contractual relationship, courts will not award such damages.

Of course, contractors should be diligent in keeping up with developments on the project—and trying to keep the project moving where it appears that one aspect has stalled. Contractors would also be well advised that where the work will necessarily involve third-parties who can influence the project without liability themselves, they should ask their counsel about what other contractual protections may be available, such as the right to extensions of time, or other exculpations from liability for delay upon the happening of certain events.

About the author: Thomas H. Welby, an attorney and licensed professional engineer, is General Counsel to the Construction Industry Council of Westchester and the Hudson Valley, and is the Founder of, and Senior Counsel to the law firm of Welby, Brady & Greenblatt, LLP, with offices located throughout the Tri-State/Greater Metropolitan Region. Gregory J. Spaun, General Counsel to the Queens and Bronx Building Association, and an attorney and a partner with the firm, co-authors this series with Mr. Welby.

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Court Declines to Cancel Lien where Defect wasn’t Apparent on Face of Document

In this column, we often remind our readers that a mechanic’s lien is a powerful tool for an unpaid contractor to obtain payment. For that reason, the target of the lien, either the property owner or the affected upstream contractor(s), often wants (or needs) to see the lien removed just as quickly as it was asserted. Section 19 of the Lien Law provides such persons and entities with the ability to have liens quickly discharged, but only if they are defective on their face. In the recent case of Pizzarotti, LLC v Gravity Construction Corp., a court reminded us that a defect on the face of the lien is one that is evident by looking only to the face of the lien, and without reference to any documents other than the lien itself.

Background

Pizzarotti was the construction manager for the construction of a residential building in Manhattan. Pizzarotti retained Gravity Construction as its masonry subcontractor. In June of 2019, Gravity submitted its final application for payment to Pizzarotti. Not having received its claimed payment, in November of 2020, Gravity filed several mechanic’s liens, seeking a total of $830,652.83. In these mechanic’s liens, Gravity alleged that its last date of work was April 27, 2020, which was within the statutory eight-month window in which to file the liens.

Within days of the filing of the mechanic’s liens, Pizzarotti commenced a proceeding, pursuant to Section 19 of the Lien Law, to have Gravity’s liens discharged as defective. In support of its petition, Pizzarotti not only noted that Gravity’s final application for payment was dated in June of 2019 (and, thus, the liens filed in November of 2020 would be untimely), but that pursuant to Governor Cuomo’s Executive Order 202, it was impossible for Gravity—or anyone else—to have been on site on April 27, 2020. Pizzarotti argued that Gravity’s listing of this date in its mechanic’s liens was simply a manufactured attempt to avoid the liens being dismissed as untimely.

Decision

The court denied Pizzarotti’s petition, finding that there was nothing invalid on the face of the liens because November 17, 2020, the date on which the liens were filed, was within eight months of April 27, 2020, the date listed in the liens as the last date of work. Following well settled appellate case law, the court held that to the extent that Pizzarotti disputed the facts set forth in the liens—rather than what was printed on their face—it would have to do so at trial, and the summary remedy was unavailable.

Comment

A mechanic’s lien is a powerful tool for a contractor to obtain payment, since it not only puts the world on notice that there is a claim against the property, but it often requires general and other upstream contractors whose subcontractors file such liens to go to the expense of having those liens discharged on pain of being in breach of their own contracts. Accordingly, it is natural that a contractor with a documentary defense to the claim would want the liens removed immediately. Usually, the most expeditious way to do this is to bond off the lien (and pay the associated premium). While the Pizzarotti court reminded us that the summary proceeding under Section 19 is limited to situations where the lien is defective on its face, there are other provisions in the Lien Law—such as the demand to foreclose, which, if not responded to, itself constitutes grounds for the expeditious discharge of a lien—which allow such issues to be determined more rapidly than in a typical lawsuit. In that regard, owners and general and other upstream contractors would be advised to consult with experienced construction counsel when a mechanic’s lien is filed against a property to determine whether it can be removed more quickly than the seeming geologic speed at which your average lawsuit progresses.

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Failure to Include Monetary Demand Dooms Contractor’s Claim for Delay Damages

Several months ago, this column told of the harsh consequences faced by a contractor who did not strictly follow the notice provisions of his contract, and how such failure ultimately doomed an otherwise valid claim of over $2 million. This month, we note of the case of BG National Plumbing & Heating v New York City School Construction Authority, where an appellate court similarly doomed a contractor’s monetary claim. However, this case, unlike that previous case, involved a statutory, rather than a contractual, notice of claim.

Background

In May of 2012, BG National Plumbing and Heating was awarded a contract to perform electrical upgrades for the New York City School Construction Authority. The work was scheduled to take 730 days, and BG received its Notice to Proceed from the SCA on June 18, 2012. Eighteen months into its work, BG filed a Notice of Claim against the SCA, claiming that it was entitled to an extension of the contractual completion date by 243 days because of certain SCA-caused delays. Crucially, this Notice of Claim did not include any monetary demand.

In September of 2014, BG sued the SCA, filing a summons with notice (an abbreviated document that does not require one to set forth its damages in detail). The parties attempted to work out their dispute (which included completing the project, which occurred on December 9, 2015), and they agreed that BG could file its complaint (the document in which a party is required to set forth the details of their claim) once it received an expert’s report detailing what those damages were. BG received that report on March 13, 2017, and it filed its complaint on October 3, 2017, seeking $2,455,740 in delay damages. The SCA then moved to dismiss BG’s lawsuit, arguing that as the Notice of Claim failed to apprize the SCA of the monetary claim, BG was prohibited from pursuing it in court. In response to the motion, on July 17, 2018, BG cross-moved to amend its Notice of Claim to include the monetary claim.

Decision

The motion court granted the SCA’s motion, denied BG’s cross-motion, and dismissed BG’s complaint, finding that the Notice of Claim filed by BG was defective in that it failed to set forth BG’s claimed damages in detail. In doing so, the motion court noted that damages are generally ascertainable upon the substantial completion of a construction project, which occurred here in December of 2015. However, even giving BG the benefit of the doubt, the motion court noted that BG received the expert report setting forth its delay damages in March of 2017, and even assuming that its claim was not ascertainable until that date, saw that BG failed to take any action until it was faced with a motion to dismiss its lawsuit sixteen months later.

BG appealed, and the appellate court affirmed the court below. In doing so, the appellate court held that while a Notice of Claim can be amended to correct good faith and non-prejudicial mistakes, it cannot substantively change the theory of liability—which the proposed amended Notice of Claim would do by, for the first time, including a monetary component. The appellate court also noted the “inordinate delay” between the time when BG first became aware of the nature and extent of its damages, and when it acted to amend its Notice of Claim.

Comment

When seeking to make a claim against the public purse, there are—in additional to contractual provisions requiring notice—often statutory or other regulatory provisions requiring contractors to make notice of their claim. These provisions can be found scattered in various statutes (in this case, Section 1744 of the Public Authorities Law, which requires a Notice of Claim to be filed before suing the New York City School Construction Authority) or, in the case of some cities and counties, buried deep in their city/county charters. As we saw in BG National, failure to strictly comply with these statutory provisions can be just as fatal as failing to comply with contractual notice provisions. Accordingly, contractors who believe that they have claims against a public owner would be well advised to consult with experienced construction counsel to be sure that their claims are asserted in a way that complies with both the contractual and statutory/regulatory notice of claim provisions.

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Court Relies on Evidence Outside Contract to Determine Parties’ Intent as to Calculation of Pricing

A consistent theme of this column has been that at the end of the day, what is expressed in the parties’ contract will control their relationship—and ultimately control what a court does when something goes awry with that relationship. However, what happens when the parties’ intent, as expressed in their contract, is not clear? The recent case of Top Grade Excavating New York, Inc. v HDMI Holdings LLC shows us that under such circumstances, a court can rely on outside evidence to determine what the parties intended back when they entered into the contract.

Background

In October of 2014, Top Grade Excavating New York entered into a subcontract with Airitan Management Corp. by which Top Grade was subcontracted to perform certain excavation, foundation, and concrete slab work at the construction site owned by HDMI Holdings. The form of contract was Top Grade’s (bare bones) proposal form, which stated that it was based on certain specified drawings and a geotechnical investigation report. The scope of work (which was scattered between various sections of the proposal) described various charges for excavation, and included two lines labeled “Total Rock Breaking Price” and “Total Price for Excavation”. However, below the line labeled “Total Price for Excavation” was a disclaimer stating “no rock breaking, no contaminated dirt, no dewatering, no existing concrete footing and wall demolition, no metal tank or other things”. Later on the proposal form, there were prices (on a per cubic yard basis) for “Rock 1a breaking”, “Rock breaking for elevator pit”, and “Hauling”. Unfortunately, there was nothing in the proposal form defining how the removed rock was to be quantified, or how Top Grade would be paid if it had to break and haul both 1a rock and rock for the elevator pit (which Top Grade ultimately did).

A dispute arose as to how Top Grade was to be paid for the work it performed on the job, and Top Grade eventually filed (and sued to foreclose) a mechanic’s lien it filed against HDMI’s property.  The case ultimately went to a non-jury trial. At trial, Airitan’s principal testified that the contract was a fixed price contract, as was evidenced by the lines “Total Rock Breaking Price” and “Total Price for Excavation”. However, when confronted with change orders that Airitan had previously approved for additional rock breaking, Airitan’s witness then testified that the quantity of rock should be measured by the drawings which showed the rock in place, and not by truckload quantity (which is certainly greater). Top Grade’s principal testified that Airitan’s approval of the earlier change orders stood as an acknowledgement that Top Grade was entitled to compensation for the extra rock removal. As to the calculation of the quantity, Top Grade’s witness testified that measurement by the truckload was the industry standard, even if such number deviated from the Department of Building’s measurements—as was evidenced by Airitan passing along these charges upstream, unmodified, to HDMI for payment.

Decision

The trial court credited the testimony of Top Grade’s witness that the contract was not a lump sum contract, and that truckload measurement was the correct measurement for the quantity of removed rock—even if it was a larger measurement than what the drawings showed. Airitan appealed (and abandoned its lump-sum argument), focusing on the argument that the trial court erred in accepting outside testimony that the truckload measure was the proper measure for billing for rock removal. The appellate court rejected that argument, finding that the contract was silent as to how the quantity of broken rock was to be measured. In light of this silence, and guided by long standing case law, the appellate court held that the trial court “properly considered extrinsic evidence in determining whether the quantity of excavated broken rock was to be based on the dimensions of the excavation, i.e., the volume of the rock in its compacted, unbroken, undisturbed state or the size of the containers it filled after being excavated and broken”.

Comment

While the law is well settled that a court cannot accept outside evidence where a contract is clear on a subject, Top Grade stands for the principle that where a contract is either silent or ambiguous on such a subject, then a court can rely on outside evidence (either documents or testimony, or both) to fill in the blank. Clearly, in such a situation, someone’s understanding of what the contract provided for is not going to prevail. That understanding may affect either a minor, or major, term of the contract—and, as we saw in Top Grade, it can even affect a monetary term of the contract, turning what a contractor believed was a profitable contract into an unprofitable one.

In order to prevent a court from telling a contractor what they meant at the time they signed the contract, such contractor should make sure that all reasonably foreseeable eventualities (such as what, and how, an excavator would be entitled to compensation in the likely event that they hit extra rock) are addressed in the contract to each party’s satisfaction. Consulting with experienced construction counsel to be sure that there is clarity and specificity in a contract would limit a court’s role to enforcing what is already written, while depriving it of any blanks to fill in.

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100

Another Valid Claim is Buried in the Graveyard of Lack of Contractual Notice

We have written on more than one occasion about how a construction contract is meant to define the relationship between the parties, and that absent a provision which violates public policy (pay-if-paid, pre-emptive lien waivers, indemnification of a party for its own negligence, etc.), the contract will be enforced as written. The provisions of these contracts which seems to be invoked most frequently are the provisions for delivering notice of claims to the owner for extra, additional, or even delay compensation. In the recent case of APS Contractors, Inc. v New York City Housing Authority, an appellate court again showed us the importance of strict compliance with these contractual notice of claim provisions.  

Background

In May of 2014, APS Contractors entered into a contract the New York City Housing Authority where APS was to be NYCHA’s general contractor for a façade and roofing project at the Pink Houses in Brooklyn. The contract contained a provision, at Section 32(a), requiring the contractor to file a notice of intention to file a claim within 20 days after such claim arose, or else such claim was waived.

On April 28, 2017, the Certificate of Final Acceptance was issued, and on May 9, 2017, APS submitted a document that it denominated “Verified and Itemized Statement and Notice of Claim”, which asserted three claims, as follows: $1,416,543 for additional work for lead abatement and painting at the railings; $512,727.50 for additional work for temporary roofing; and $114,020 for additional work in removing certain concrete patching. No payment was made on this claim, and APS commenced its lawsuit to recover on these claims on May 17, 2018.

NYCHA ultimately moved to dismiss APS’s lawsuit, citing to Section 32(a) of the contract. NYCHA argued that APS had knowledge of the lead abatement claim on April 20, 2016, the date on which NYCHA advised that it would be calculating APS’s compensation in a manner different than that proffered by APS. Similarly, NYCHA argued that APS had knowledge of the temporary roofing claim on January 16, 2016, when NYCHA first rejected its request for additional compensation, claiming that temporary roofing was included in the contract. Likewise, as to the concrete repair claim, NYCHA argued that APS had knowledge as early as May 11, 2016, the date on which NYCHA indicated that would not provide APS with additional compensation for this work. APS argued that voluminous email correspondence adequately advised NYCHA of the fact that APS was making claim for these additional monies, and that this correspondence otherwise satisfied the requirements of the contract.

Decision

The motion court denied NYCHA’s motion as it related to the lead abatement claim, finding that the significant amount of email correspondence apprized NYCHA of APS’s intent to file a claim within the contractual deadline, and provided the requisite information. However, the court granted NYCHA’s motion as it related to the other two claims, finding that there was no similar chain of correspondence that would have apprized NYCHA that APS would be making a claim for those sums.

On appeal, the appellate court reversed the motion court and dismissed the complaint, finding that the motion court had erred in finding the email correspondence satisfied the notice of claim requirement. In doing so, the appellate court held that the contract was specific that the notice of claim had to be denominated as such, had to contain certain specified information, and had to be clear that APS intended to pursue the claim for compensation. The appellate court found that the email correspondence met none of these requirements.

Comment

APS is yet another reminder that in most circumstances, contractual conditions precedent will be strictly enforced. Here, what appeared to be over $2 million in valid claims for extra and additional work ended up dismissed for a simple failure to follow contractual formalities. While APS’s claims ended up buried in the graveyard of inadequate notice, this did not need to happen.

It goes without saying that contractors would be well advised to follow such contractual conditions precedent to the letter so that you are not in the position of having to later argue, like APS, that cobbled together correspondence constitutes the notice required by the contract. Often, and unfortunately, by the time the contractor recognizes that it is up against a deadline to submit a notice of claim, that deadline may have already passed. Your project people must learn to recognize the actions and correspondence from the Owner that trigger the Notice stop watch.  In that regard, contractors should examine their contracts with experienced construction counsel so that they can—at the outset of the job—have a checklist of what to submit when a claim arises, and the deadline for doing so.

If you would like more information regarding this topic please contact Thomas H. Welby at twelby@wbgllp.com or call (914) 428-2100