The Perils Of Doing Business With DBES On A Cost Plus Basis

On March 10, 2011, following a four-week criminal trial, a federal jury found Zohrab B. Marashlian, the former President of Perini Corporation’s Civil Division (“Perini”), guilty of fraud and conspiracy to launder money. Two days later he took his own life. What led to this sad and unfortunate outcome? Based on information obtained from the U.S. District Court’s file in United States v. Zohrab Marashlian, Docket No. CR-08-900, I will attempt to answer this question.

Personal History:

Mr. Marashlian was President of Perini’s Civil Division from 1997 to 2007. He was born in Aleppo, Syria in 1944 to an Annenian family. He earned his civil engineering degree from the American University of Beirut, Lebanon, and immigrated to the United States in 1971. He later earned an MBA from Columbia University. Shortly after arriving in America, he was employed by Perini as an office engineer, and through hard work and ambition rose to President. Zohrab Marashlian was responsible for constructing and rehabilitating many high profile projects including highways, bridges, subways, tunnels, and waste water treatment facilities. By all accounts, he was a wellrespected executive, and a friend to many in the heavy construction industry.

The Criminal Charges:

The criminal charges against Mr. Marashlian arose out of representations, made to government contracting agencies on certain federally-funded projects, that Perini would use disadvantaged business enterprises (“DBEs”)1 to perform certain percentages of work, as required under the public contracts awarded to and performed by Perini. Instead of having the DBE subcontractors perform the specified work, however, the jury found that Zohrab knowingly used the DBE subcontractors as “fronts” for non-DBE companies, which actually performed the work set aside for the DBE companies.

The Indictment against Mr. Marashlian, which included numerous counts of mail fraud, wire fraud and money laundering, stated in pertinent part as follows:

The defendants Zohrab B. Marashlian and … others devised a scheme to defraud government contractirig agencies … by falsely representing in proposals and other documents submitted by Perini to those agencies for public works contracts … that DBE subcontractors would perform commercially useful functions in satisfaction of the DBE requirements of those public works contracts.

Contrary to the representations made by Perini, when Perini was awarded the public works contracts, Marashlian … and others did not have the DBE subcontractors perform commercially useful functions on the public works contracts. Instead Marashlian . . . and others used non-DBE subcontractors to perform work on the public works contracts that should have been performed by the DBE subcontractors.

It was part of the scheme to defraud that the defendants Zohrab B. Marashlian … and others caused non-DBE subcontractors to list their employees and supervisors on the payrolls of the DBE subcontractors, and order supplies and materials through the DBE subcontractors, to create the appearance that the DBE subcontractors were performing commercially useful functions on the public works contracts. Marashlian …further caused Perini to falsely certify to [public contracting agencies] that the DBE subcontractors performed DBE subcontract work on the public works contracts when, in truth and fact, as Marashlian … well knew and believed, the DBE subcontract work on the public works contracts was performed by non-DBE subcontractors (¬∂¬∂ 13-15 of the Indictment, filed December 18, 2008).

According to the government, Marashlian’s false representations induced, aided and abetted the award of more than $284 million in public contracts to Perini2 During the performance of these contracts, Zohrab and others took steps to maintain the illusion that the DBE subcontractors were actually performing the work, by arranging financing and laundering payments through the “front” companies. The progress payments from the public contracting agencies to Perini were deemed by the government to be financial transactions, with proceeds from a specified unlawful activity (i.e., money laundering), because, but for the fraud committed by Mr. Marashlian, Perini would not have been awarded the contract, and would not have received the progress payments. The tainted monies were then paid out, to the supervisors, workers and/or non-DBE subcontractors actually performing the work after a fee for processing the payments was deducted by the DBE (i.e., the DBE subcontractors received a fee or markup ranging from 3% to 5% of their costs). As a result of these frauds, the prosecution pointed out, Mr. Marashlian individually benefitted from the receipt of substantial payments, in the form of increased corporate salary and bonuses, totaling $14 million from 1994 through 2007. There was, however, no indication in the court papers that Mr. Marashlian personally received kickbacks from the DBE or non-DBE subcontractors or their principals.

The “Commercially Useful Function” Requirement:

In order to receive Federal highway funds, New York was required to have a DBE Program meeting Federal requirements and has done so by adopting them under 17 NYCRR35.3.

Under the relevant DBE Programs established by New York State and City agencies (the ”NY-DBE Programs”), general contractors are permitted to count toward the attainment of their DBE percentage goals only funds paid to DBE companies that perform a “commercially useful function” in the performance of a contract. Under such NY-DBE Programs, and the associated federal regulations, a DBE company performs a “commercially useful function” when it: (a) is responsible for the execution of a distinct element of the work of a contract; (b) carries out its responsibilities by actually performing, managing and supervising the work involved; and (c) furnishes all supervision, labor, tools, equipment, materials and supplies necessary to perform that distinct element of the contract work. Pursuant to federal regulations, a DBE does not perform a “commercially useful function,” if its role is limited to that of an extra participant in a transaction, contract, or project, through which funds are merely passed in order to obtain the appearance ofDBE participation in a contract.

In order to participate in the NY-DBE Programs, a minority and/or female owned company has to be certified as a DBE by the NYSDOT or the City of New York. “DBE certification” means that a general contractor can receive credit toward the attainment of its DBE percentage goals, by subcontracting work to the certified DBE company. However, the DBE company still has to perform a “commercially useful function” in order for the general contractor to receive credit; and, as you might guess, the general contractor is responsible for making sure that the DBE subcontractor performs a “commercially useful function.”

Furthermore, pursuant to New York law and federal regulations, a DBE subcontractor is prohibited from subcontracting work it is awarded in connection with its DBE status.

The Criminal Conduct:

This is where Mr. Marashlian made a serious mistake that mushroomed into criminal conduct. The prosecuting attorneys claimed, that for over a decade, Mr. Marashlian, and others working under him, repeatedly met with specialty subcontractors, and told them that in order to be awarded work by Perini, they had to bill their work through a DBE company’s name so that Perini could receive “DBE credit”. According to government witnesses, sometimes Mr. Marashlian would dictate which DBE the subcontractors should use as a “front,” and sometimes he did not care what DBE was used, as long as Perini could claim the subcontract work for DBE credit. Whether or not Mr. Marashlian was simply trying to shift the headache of complying with the DBE program away from Perini to Perini’s subcontractors, the jury was convinced that he committed fraud, by directing or causing the specialty subcontractors to transfer their management and workers to the books of DBE companies, and having those DBE companies pass on fraudulent invoices to Perini.

Recommendation:

Any person or company, when selecting a DBE subcontractor to perform a certain scope of work on a public contract, should avoid doing business with DBE subcontractors on a ”time and material” or “cost plus” basis, unless the DBE can demonstrate a history of performing the subcontract work and managing its own work, including supervising, hiring and firing of employees, and the performance of all administrative functions.

Doing business with certified DBE subcontractors that have nothing more than an office and a handful of clerical employees to run a payroll, purchase materials and pay project related invoices is clearly not enough to meet DBE requirements, and will likely draw the scrutiny of government investigators. Everyone in the heavy construction industry should recognize by now that a DBE subcontractor does not perform a “commercially useful function,” if its role is limited to that of an extra participant in a transaction, contract or project, through which funds are passed in order to obtain the appearance ofDBE performance of work on a project. The u.s. Attorney clearly stated in a memorandum filed in the subj ect case that

DBE companies who agree to act as a ”hilling” or ”payroll” service for a fee, generally cease to operate as legitimate contracting companies. The DBE company that acts as a “front” for a legitimate subcontractor or the subcontractors’ employees have the effect of gutting the DBE, reducing or eliminating the need for most employees from the DBE and preventing the company from developing contract experience and increasing in size – all goals ofDBE programs.

If you can’t find a capable DBE subcontractor to meet the contract’s DBE requirements, disclose that fact to the public contracting agency at the outset, and request a reduction of the DBE goals set by the agency. Where the public agency determines that “good faith efforts” have been made by the general contractor, and competent DBE subcontractors are not available, the agency should waive compliance with the DBE goal. For example, according to the government’s court papers, during the time frame involved in Mr. Marashlian’s case, State agencies often reduced DBE “goals” by up to 50% or more, at the request of general contractors, who had attempted, unsuccessfully, to comply.

Shifting the Risk of Doing Business with DBE Subcontractors back to the Government:

The time may have also come for contractors to decline taking on the risk associated with these government set-asides. Besides the mistakes made by Mr. Marashlian and Perini, a number of other well-known and reputable heavy construction contractors have reached multimillion dollar civil settlements for doing business with DBE companies that failed to perform a “commercially useful function”. In competitively-bid construction contracts, why should a contractor be asked to take on the added risk of having to find competent DBE subcontractors, and then hope that such companies are capable of fully performing their scope of work on schedule, and in accordance with plans and specifications? In order to level the playing field among all general contractors bidding the work, perhaps the United States Department of Transportation (i.e., the federal agency responsible for issuing the regulations governing the DBE Program) should make the local governmental agency responsible for selecting one or more competent DBE subcontractors to perform a defined scope of work as separate prime contractors, and then have the government agree to assume the risk that the DBE prime contractor may fail to perform. The government could select the appropriate DBE contractors through a separate request for proposal (“RFP”) or competitive bidding process, and define the scope of work to be performed by the DBE companies in the main prime contract. This type of arrangement would enable the general contractor to focus on what it does best – – managing, scheduling and constructing the Project, without the worry of trying to increase the participation of competent DBE’s in federally-funded public construction contracts. Although this could cause some of the problems that are commonly associated with “Wicks Law” projects in New York, it would eliminate the risk, now faced by general contractors, of being criminally prosecuted for intentionally or unintentionally crossing over the line in order to meet the requirements of the Federal DBE Program.

Hopefully, every executive in the construction industry wi11leam a lesson from the above story, and pass that lesson on to younger members of our industry in order to prevent a similar occurrence in the future.


1 A DBE is a small, for-profit business concern that is at least 51 % owned and controlled by socially and economically disadvantaged individuals. The firm must be operational, independent and operate in a selfsufficient manner. The owners must meet the federal definition of “socially and economically disadvantaged” (Women, minorities, or individuals who can document their disadvantage; all must also demonstrate that their adjusted personal net worth is no more than $1.32 million). Owners must possess the power and expertise to control the daily operations and management of the firm, and be able to establish at least 51 % ownership through real and substantial investments of capital. If anyone of these conditions is not met, the company does not qualify as a DBE. (49 C.F.R. 26)

2 On October 30, 2009, Perini Corporation entered a civil settlement with the government in connection with the contract frauds outlined in the indictment. Perini paid $9.75 million in settlement, to the government to avoid any actions against Perini Corporation, including actions for false claims against Perini. These monies eliminated any profit from the four contracts referenced in the Indictment. Perini also agreed with the USDOT to take steps to insure compliance with the DBE program on future public works contracts.

Shifting or Accepting the Risk for Differing Site Conditions in Construction Contracts

INTRODUCTION

A comprehensive investigation of subsurface conditions before the design and construction of a project is generally considered a worthwhile investment that will, for the most part, eliminate surprises and costly change orders to the construction contract. Sometimes, however, even the most comprehensive investigation does not eliminate all surprises during performance of the construction contract and the Owner, Engineer and Architect must decide how to allocate the risk for such unanticipated subsurface conditions. If the risk is shifted to the Contractor, one would reasonably expect that the Contractor would add a contingency to its bid price in order to cover the risk of such unforeseen conditions. By adding a differing site conditions clause to the construction contract, however, the Owner can accept the risk and agree to issue the contractor a change order in the event of such unforeseen conditions. Set forth below is a discussion of how to manage these risks through the construction contract documents and of the pitfalls to avoid in preparing such contract documents, which normally include soil boring logs and a geotechnical report.

Key Contract Clauses and Related Court Decisions

1. Differing Site Conditions, Changed Conditions and Concealed or Unknown Conditions

The terms “differing site conditions”, “changed conditions”, and “concealed or unknown conditions” are perhaps best defined by the Federal Acquisition Regulations as follows:

(1) subsurface, latent or physical conditions at the site materially different from those indicated in the Contract; or
(2) unknown physical conditions at the site of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract (48 CFR Section 52.243.5).

In Other Words . . .
+ Type I = Bid documents differ significantly from the actual site conditions

+ Type II = Bid documents show nothing, but site conditions are significantly different than what would normally be expected

New York law allows a contractor to prevail on a differing site condition claim, but the contractor is first required to prove six elements:

(1) the contract documents must have affirmatively indicated the subsurface conditions; (2) plaintiff must have acted as a reasonably prudent contractor in interpreting the contract documents; (3) plaintiff must have reasonably relied on the indications of subsurface conditions in the contract; (4) the subsurface conditions actually encountered must have differed materially from those indicated in the contract; (5) the actual subsurface conditions encountered must have been reasonably unforeseeable; (6) and plaintiff’s claimed damages‚Ķmust have been solely attributable to such materially different subsurface conditions.

Fruin-Colnon Corp. v. Niagara Frontier Transp. Authority, 180 A.D.2d 222, 226, 585 N.Y.S.2d 248 (4th Dept. 1992). “[T]o the extent [that] the conditions described in the contract materialize, the contractor bears the risk, while the government assumes the risks for conditions [that] the contract documents fail to disclose.” Id. at 227.

2. Shifting the Risk to the Contractor by use of Disclaimer and Exculpatory Clauses

As a defense against differing site condition claims, Owner’s have successfully enforced disclaimer and exculpatory clauses in the bidding documents. Typically, a disclaimer or exculpatory clause states that the conditions depicted on the bidding documents are not to be treated as a representation of the actual conditions and the information is not to be substituted for the personal investigation to be performed by the contractor prior to bidding on the documents. A. S. Wilkstrom, Inc. v. State, 52 A.D.2d 658, 381 N.Y.S.2d 1010 (3d Dept. 1976).

Several types of Contract Clauses attempt to limit the Contractor’s right to make or prevent such claims. Disclaimer and exculpatory clauses are used by Owners to shift the risk for “differing site conditions:, “changed conditions” or “concealed or unknown conditions” to the Contractor.

Disclaimer clauses, for example, are used to avoid responsibility for incorrect or incomplete information which may be contained in the Contract Drawings and Specifications. Such clauses generally require the Contractor to investigate the site and determine the risks associated with the job, state that the Owner does not warrant the information it provides, and state that the information is provided for estimating purposes only. For example, the New York State Department of Transportation has previously used a clause which disclaims the accuracy of stated conditions and quantities. It reads as follows:

SPECIAL NOTE – Unclassified Excavation:
The excavation table appearing on this sheet was prepared by the State from the best information available. The Contractor’s attention is called to the fact that conditions and quantities, as shown on the table are estimated and not actual, and in any event they are not to be determined or considered by the Contractor as a warranty or a representation by the Superintendent of actual field conditions or quantities.

With respect to the State’s production of soil boring logs along with plans, specifications and other bid documents, which are used by a prospective Contractor in preparing its bid, the State has also used the following clause effectively:

This information is intended for State design purposes only, and is made available to bidders only that they may have access to identical subsurface information available to the State. It is presented in good faith, but is not intended as a substitute for the personal investigations, interpretations or judgments of the Contractor.

Another form of disclaimer requires the Contractor to investigate the site and to determine the risks associated with the job. In Article III of the State’s Standard form contract there is a requirement that the Contractor examine the Contract Documents and the site of the proposed Work which reads as follows:

ARTICLE 3. EXAMINATION OF DOCUMENTS AND SITE.
Contractor agrees that before making his proposal he carefully examined the Contract Documents, together with the site of the proposed Work, as well as its surrounding territory, it is fully informed regarding all of the conditions affecting the work to be done and labor and materials to be furnished for the completion of this contract, including the existence of poles, wires, pipes and other facilities and structures of municipal and other public service corporations on, over or under the site, and that this information was secured by personal investigation and research and not from the estimates or records of the department, and that he will make no claim against the State by reason of estimates, tests or representations of any officer or agent of the State.2

Despite a disclaimer clause, the State may still be liable “if said conditions are not as represented and (1) inspection would have been unavailing to reveal the incorrectness of the representations or (2) the representations were made in bad faith.” A. S. Wilkstrom, Inc., 52 A.D.2d 658, 381 N.Y.S.2d 1010 (3d Dept. 1976).

The State and for that matter any Owner should disclose all information it has regarding subsoil conditions from either tests it has performed or prior knowledge of the conditions, but if the disclosed information was the same as the undisclosed information and the bid would not have differed otherwise, the State or the Owner is not liable. Id. By signing an agreement which stated that the documents make no representation regarding existing sub-surface conditions, character and extent of the soil data or other subsurface conditions to be encountered during the work and no guarantee as to their accuracy, the contractor waived the right to hold the architect liable unless the architect withheld information which would have affected the amount of the bid. Wrecking Corp. of America v. Memorial Hospital for Cancer and Allied Diseases, 63 A.D.2d 615, 405 N.Y.S.2d 83 (1st Dept. 1978).

In Wrecking Corporation of America, the agreement between the parties clearly imposed upon the excavation subcontractor the responsibility and risk of subsurface conditions. One part of the Contract provided that “no representation is made by the General Contractor, Owner, Architect or Engineer in any Contract Document regarding the existing subsurface conditions”, and in another part of the contract it further provided that “the Owner, Architect and Consulting Engineers make no representations regarding the character and extent of the soil data or other subsurface conditions to be encountered during the Work and no guaranty as to their accuracy or interpretation is made or intended”. Based on these Contract provisions, the excavation subcontractor’s complaint that subsurface conditions encountered differed materially from those represented in the design drawings furnished by the Contractor and the Owner was dismissed. The Court found that plaintiff clearly assumed full and complete responsibility for all excavation and construction costs relating to the foundation, including total responsibility for subsurface conditions. Also with respect to the excavation subcontractor’s claim that the Owner withheld relevant information and failed to determine subsurface conditions in a reasonable manner it was found that there was no showing that the as-built drawings, which plaintiff claimed were not supplied to it at the time of bid, were actually in existence, let alone that they were in the Owner’s possession or control and were withheld by it. The usefulness of the as-built drawings was also seriously questioned in the depositions of the parties.

In Depot Const. Corp. v. State of New York, the State included a disclaimer in the bidding documents stating that the information provided was for “design purposes only” and was “not intended as a substitute for personal investigations, interpretations or judgment of the Contractor.” Depot Const. Corp. v. State of New York, 19 N.Y.2d 109, 114, 224 N.E.2d 866 (N.Y. 1967). The State was not liable for fraudulent misrepresentation when it provided to the contractor the boring data results, as well as any other information it had on the subsoil conditions. Id. “No reasonable bidder could have assigned to the borings a more significant role of specificity; or could have expected them to represent more than a small number of samplings over a large area.” Id. Therefore, the State, by providing all the information it had on underground conditions and using a disclaimer in the bidding documents, successfully transferred the risk of differing site conditions to the contractor.

On the other hand, the reasonableness of the contractor’s reliance on the bidding documents may depend on the timing requirements for the bid. For example, the State was liable for fraudulent misrepresentation when after ten years of investigation, the bidding documents indicated that the “boulders‚Ķwere the least predominant” in the soil, when in reality, the contractor found “nested boulders” which were “so large and numerous and so close together as not to allow room for pile insertions.” Conduit and Foundation Corp. v. State of New York, 74 A.D.2d 684, 685, 425 N.Y.S.2d 874, 877 (3d Dept. 1980). The court found it was reasonable for the contractor to depend on the bidding documents as an accurate representation of the subsoil conditions since the State had investigated the area for over ten years, the contractor only had one month to prepare its bid, and did not have sufficient time to conduct its own subsoil inspections. Id.

Similarly, the State was liable for fraudulent misrepresentation despite a disclaimer clause in the bidding documents when the State knew exactly how much work would need to be performed to obtain acceptable subsoil conditions, but intentionally specified only half of such work in the bidding documents. County Asphalt, Inc. v. State of New York, 40 A.D.2d 26, 337 N.Y.S.2d 415 (3d Dept. 1972). The fact that the contractor’s bid would have been significantly higher if it had known of the actual amount of work to be performed and that the contractor only had three weeks to prepare its bid weighed against the State, because in such conditions, it was reasonable for the contractor to rely on the bidding documents as an accurate representation of the subsoil conditions. Id. The limited amount of time to prepare the bid also meant the contractor did not have sufficient time to perform an independent subsurface exploration to determine the actual conditions. Id.

3. Misrepresentation Theory

“To rely on fraudulent misrepresentation, claimant [has] to prove that the additional work performed resulted directly from the State’s [or Owner’s] concealment or nondisclosure of material facts either known to it or within its possession.” D. A. Elia Const. Corp., v. New York State Thruway Authority, 289 A.D.2d 665, 666, 734 N.Y.S.2d 295, 297 (3d Dept. 2001). A clause in the bid documents advising bidders to conduct their own field inspections can be relied on as a defense, as long as there is no evidence that sufficiently thorough inspection could not have been made before the contractor submitted its bid. Id. Since the contractor failed to perform its own inspection, the contractor “could not reasonably rely on the bid documents for anymore than an approximation of the repair areas.” Id.

Despite a disclaimer clause, the State may still be liable “if said conditions are not as represented and (1) inspection would have been unavailing to reveal the incorrectness of the representations or (2) the representations were made in bad faith.” A. S. Wilkstrom, Inc., 52 A.D.2d 658, 381 N.Y.S.2d 1010 (3d Dept. 1976).

While disclaimers can be effective to protect an Owner from a Contractor’s claim of changed conditions, such clauses will be strictly construed against Owners. For example, in Andrew Catapano Company v. The City of New York, 116 Misc.2d 163, 165, 455 N.Y.S.2d 144 (New York, 1980) the Court determined that even where a contract disclaimed responsibility for conditions “on, about or above the site,” the Owner had not disclaimed responsibility for subsurface conditions, because of the stated language and because the changed conditions clause in the Contract specifically provided for adjustments in the event of unanticipated subsurface conditions.

Such disclaimers will also be unavailing when conditions represented by the Owner are highly inaccurate. In Warren Bros. Company v. New York State Thruway Authority, 34 A.D.2d 97, 99, 309 N.Y.S.2d 450, 452 Aff’d. 34 N.Y.S.2d 770, 358 N.Y.S.2d 139, the court stated:

In a construction contract between the State and an individual, which contains representations as to existing conditions affecting work thereunder as well as an exculpatory clause relieving the State of liability and requiring personal inspection of the contract site, liability, nevertheless, may attach to the State if said conditions are not as represented and (1) inspection would have been unavailing to reveal the incorrectness of the representations or (2) the representations were made in bad faith.

Exculpatory clauses meant to relieve an Owner of liability for the information that it provides and for damages incurred due to changed conditions, are generally valid and enforceable, even when they are intended to relieve the Owner of responsibility for its own negligence. Such Exculpatory clauses will, however, not insulate an Owner from liability where the conditions are not as represented in the Contract and inspection by the Contractor would not reveal the representations to be false Rusciano Construction Corp. v. The State of New York, 37 A.D.2d 745, 746, 232 N.Y.S.2d 21, 24 (3rd Dept., 1971). Furthermore, a Contractor is not to be foreclosed by standard exculpatory clauses which place the burden to investigate the site and discover potential problems wholly upon it, when the State or municipality is chargeable with knowledge of their existence and location (see Laura Roofing & Renovation Co., Inc., v. The Board of Education of the City of New York, 57 A.D.2d 586, 393 N.Y.S.2d 593 (2nd Dept., 1977)). Without exception, an exculpatory clause will not insulate an Owner from liability when the Owner intentionally misrepresents the conditions. Rusciano Construction Corp. v. State of New York, 37 A.D.2d 745, 323 N.Y.S.2d 21 (3rd Dept., 1971). The bottom line is that even when such disclaimer and exculpatory clauses are included in a contract, an Owner may be liable for both innocent and intentional misrepresentations. Under either theory, however, the misrepresentation must be material in order for a Contractor to recover damages. See A.S. Wilkstrom, Inc. v. State of New York, 52 A.D.2d 658, 381 N.Y.S.2d 1010 (3rd Dept., 1976).

4. Owner’s Acceptance of the Risk for Changed Conditions

If the Owner decides to accept the risk for unforeseen subsurface conditions, there are many ways to address this in the construction contract. For example, AIA Document A201 – 1997 provides the following clause covering changed conditions but does not limit the location of the condition:

4.3.4 Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than 21 days after first observance of the conditions. The Architect will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor’s cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the contract is justified, the Architect shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within 21 days after the Architect has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to the Architect for initial determination, subject to further proceedings pursuant to Paragraph 4.4. (underlining added for emphasis)

Unless otherwise addressed in the Contract Specifications, the above Changed Conditions clause would permit the Contractor to recover additional costs associated with a subsurface condition, such as rock, which differs materially from what was indicated in the Contract Documents (e.g. soil borings, geotechnical engineering reports, or geological profiles). If the Contractor has no control over the extent of soil borings (e.g. quantity, quality and depth) taken by the Owner or other geotechnical studies performed on behalf of the Owner, it would seem fair that the risk of such changes in subsurface conditions should be carried by the Owner. The Owner, however, should be cautious in how the fair and reasonable value of the necessary extra work is determined. For example, having the Contractor insert a unit price for the removal and disposal of increased quantities of rock in its bid proposal up front may not always work in favor of the Owner as the real cost will depend on the actual quantity and character of the rock to be removed. Negotiating a fair and reasonable price for such work may be the best alternative depending on the size of the Project and the parties involved.

5. Conclusion

The geotechnical engineer and/or design consultant needs to gather all available subsurface information at the planning stage of the project and to determine with the Owner and other design consultants the scope of the preliminary geotechnical investigation. Depending on a number of factors including the size of the project, the parties must then decide how to allocate risk with respect to unforeseen conditions, etc. and to draft the appropriate provisions in the construction contract to meet their objectives.

1. A.S. Wilkstrom, Inc. v. State of New York, 52 A.D.2d 658, 381 N.Y.S.2d 1010 (3rd Dept., 1976).
2. Id.

When Are Safety Measures “Infeasible”?

Many of us recall the popular poster of several decades ago which spoofed OSHA regulations by depicting a OSHA-Compliant Cowboy. The horse and rider were so encumbered by safety devices (harness and tether, goggles and gas mask, hardhat, safety net, backup alarm, etc.!), that the cowpoke was no longer able to feasibly herd cattle.

In the era immediately following the enactment of the Occupational Safety and Health Act in 1970, OSHA regulations were viewed by many in the construction industry as burdensome, expensive and unproductive. Today, most prudent and successful contractors recognize sound safety policy as an indispensable facet of overall business planning. Whether through a top-down contractual imposition of safety requirements, compliance efforts by OSHA, or simple concern for the health and safety of their employees, construction executives are going beyond the basics to implement safety programs that will give them a competitive edge going into the future.

Last month, we examined the elements of the Unanticipated Employee Misconduct Defense to an OSHA citation as a vehicle for exploring ways to improve existing safety plans to incorporate new inspection routines and paperwork systems. This would allow employers to avail themselves of the defense. Such a safety program would most likely lead to improved companywide safety and OSHA compliance In a similar way, an examination of judicial responses to other defenses, such as “greater hazard”, “impossibility” and “infeasibility” can help contractors to shape their own safety policies and procedures.

In a recent decision in a case involving the death of an employee of a demolition contractor, the Occupational Safety Health Review Commission articulated the standards established to evaluate an employer’s defense of infeasibility, stating: To carry its burden and prove its defense of infeasibility, the employer must prove:

(1) the means of compliance prescribed by the applicable standard would have been infeasible under the circumstances in that (a) its implementation would have been technologically or economically infeasible or (b) necessary work operations would be technologically or economically infeasible after its implementation, and (2) either (a) an alternative method of protection was used, or (b) there was no feasible alternative means of protection.

Secretary of Labor v. G.A. West & Company, Inc. 2004 WL 1057182 (To prevail, the employer must prove one of four elements, and then prove one of two additional elements.)

Several Federal Circuit Courts of Appeals have held that to be successful, an economic feasibility argument must demonstrate both 1.) it is extremely costly for the employer to comply with the standard and 2.) that the employer cannot absorb the cost and remain in business. Furthermore, where technological infeasibility is argued, the employer is still obligated to comply to the greatest extent possible even if it cannot comply completely. So, if the safety standard is technologically infeasible as written, the employer is not excused from employing any safety measures whatsoever.

The U.S. Court of Appeals for the D.C. Circuit recently decided a case in which the Occupational Safety and Health Review Commission upheld the findings of the Administrative Law Judge regarding a series of serious and willful citations issued to a precast concrete subcontractor. A.J. McNulty & Co. was subcontractor to Whiting-Turner Contracting Co., for the construction of a precast concrete parking structure in White Plains, New York. The floors of the parking garage were constructed out of precast “double-T’s”, weighing as much as 40 tons each. Among the several alleged violations, McNulty was cited for failing to guard floor openings by the use of railings, on floors that were in the process of being constructed. (It is noteworthy that the work was commenced in 1993, the citations were issued in 1994 and the final judicial determination was not completed until almost a decade later.) McNaulty argued that it was technologically infeasible to install guardrails around floor openings on a floor under construction. In a lengthy discussion, the Court noted that although the infeasibility defense is an affirmative defense to a charge of violating an OSHA standard, an employer mounting such a defense must show not only the infeasibility of compliance, but also that it either used alternate means of protection or that such means were infeasible. Although McNulty claimed that bolted-stanchion guardrails would have interfered with the installation of the precast concrete members, OSHA’s Compliance Officer testified that free-standing guardrails could have been used. Therefore, the Court ruled that McNulty had not satisfied all of the requirements of the infeasibility defense. (A.J. McNulty & Co. v. Secretary of Labor, 283 F.3d 328, 2002)

In 2000, the OSHRC did find that a general contractor successfully demonstrated an infeasibility defense to a citation alleging failure of the contractor to install handrails, either temporary or permanent, on a stairway used by its employees. (Secretary of Labor v. Summit Contractors, Inc.) The Compliance Officer observed the contractor’s employees moving equipment up a staircase with no handrails. OSHA argued that had the permanent hand railing been installed first, there would have been one inch of clearance for passage of the equipment. The Commission agreed with the contractor that it was infeasible to move the equipment with such little clearance. OSHA countered that temporary railings could have been fashioned to afford greater clearance to the contractor. The Commission, however, agreed with the contractor that temporary handrails would be of little use to employees using both hands to move equipment up the staircase. Accordingly, the Commission dismissed the citations. Over the past decade or so, the Commission and various Appellate Courts have considered many cases in which the contractor employed the infeasibility defense, involving trenching support systems, masonry reconstruction, swinging crane counterweights, structural concrete building systems, etc. In the majority of these cases, the defense failed.

Some OSHA safety standards contain exceptions to their own applicability. For example, the fall protection standard in Section 1926.451 exempts its application where employees are engaged in “overhand bricklaying”, defined as the process of laying bricks in masonry units such that the surface of the wall could be joined is on the opposite side of the wall from the mason requiring the mason to lean over the wall to complete the work. In 2002, the Commission considered a case wherein this very exemption was claimed by the contractor as a defense. Nevertheless, the Commission upheld the alleged violations, noting that a temporary opening for material loading to the interior scaffold was not covered by the exception and exposed the employees to a falling hazard.

The bottom line is that although there are many legal defenses to OSHA citations, it is extremely difficult to overcome the citations based on these defenses when they are considered for the first time only after the issuance of the citations. A pro-active safety policy would dictate that when the contractor recognizes that compliance with a safety standard would be difficult, inconvenient or expensive, that it affirmatively seek a variance from OSHA, or exhaustively investigate every available alternate means of providing worker safety under the circumstances.

Unpreventiable Employee Misconduct

In the Construction industry today, every responsible contractor is concerned with job site safety. Safety policy might be motivated by contractual requirements, legal requirements to comply with the Occupational Safety & Health Act (OSHA), a genuine concern for the health and well being of employees, or most probably, a combination of these factors. Despite every reasonable effort by contractors to run safe operations, accidents still happen and despite detailed safety training programs, individual employees sometimes violate safety work rules, exposing the employer/contractor to citations for violation of OSHA. When this occurs, does the contractor have any defense? The answer, as always, is “it depends”. The Occupational Safety Health Review Commission (OSHRC), the administrative judicial tribunal that hears disputes between OSHA and employers, has recognized unpreventable employee misconduct as a defense to OSHA citations under certain circumstances.

It is the aim of this article to acquaint contractors with the basics of the unpreventable employee misconduct defense so that you may chose to enhance your safety plans and training programs, and job site procedures, to protect your business from the significant adverse results of Serious OSHA Violations. Furthermore, I believe that safety programs that comply with the requirements for this defense would have the added benefit of improving overall company safety. At our CIC & BCA Winter Meeting in Palm Beach this past February, I had the pleasure of leading a roundtable discussion entitled “Understanding OSHA; Compliance, Inspections, Citations and Resolution.” The liveliness of that discussion underscored the importance of a sound safety policy. It was noted that not only have public owners determined bidders to be non-responsible based on Serious or Willful OSHA Violations, but increasingly, major corporate owners in the private sector are disqualifying bidders from their select lists based upon OSHA violations.

Complying with OSHA standards and contractually imposed safety plans is only a bare minimum. I urge each of you to be proactive in managing safety risks in your work places and establishing systems, including paperwork, not only to avoid violations and citations, but to effectively deal with citations when they are issued to you, despite your best efforts.

The OSHRC has taken the position that once the Secretary of Labor establishes a prima facie case for a particular violation, an employer may nevertheless defeat the alleged violation by a showing of unpreventable or unforeseeable employee misconduct. In order to succeed, the employer must demonstrate all of the following elements: 1) that it established a work rule to prevent the violative behavior, 2) adequately communicated the rule to its employees, 3) took steps to discover noncompliance and 4) effectively enforced safety rules when violations were discovered. (See New York Electric State & Gas v. Secretary of Labor and OSHRC, 88 F.3d 98, U.S. Court of Appeals, 2d Cir., 1996) A review of the reported cases before both the Commission and the various U.S. Circuit Courts of Appeals indicates that it is a high threshold for the contractor to prove all of the required elements of the defense. More frequently than not, the assertion of the unpreventable employee misconduct defense has failed. I believe those failures resulted in major part, from a lack of understanding of the systems and procedures necessary to establish this defense.

However, in the case of the Secretary of Labor v. Raytheon Constructors, Inc., the OSHRC upheld the contractor’s unpreventable employee misconduct defense, and vacated a Serious citation issued by OSHA. This case may serve as a guide for contractors who want to enhance their safety policy and procedures.

Raytheon was engage in the construction of an incinerator for disposal of chemical weapons at a U.S. Army facility in Oregon. Following an inspection of Raytheon’s work site, OSHA issued citations, including fifteen separate items. Half of these were classified as Serious and the rest as Other Than Serious. Raytheon filed a Notice of Contest within the required period and the matter proceeded to a hearing before the OSHRC.

Of the four required elements articulated by the Second Circuit, in the New York State Electric & Gas case, the first two elements are the easiest to establish. These are, 1) establishing a work rule to prevent violation of the OSHA standard, and 2) adequately communicating the rule to employees. Having a professionally prepared, updated company wide safety plan is basic to any corporate safety policy. Likewise are site-specific plans, tailored to the work site where the employer is working. Overly broad, boiler-plate safety plans are not adequate. Make certain that your safety plans cover all of the possible standards that may apply to your operations. All work rules must be in writing. It is not sufficient to merely communicate the work rules and safety plan to your employees. You must have a written record of that communication (If it ain’t in writing, it didn’t happen.) When the work rules and safety plan are communicated to employees either during orientation or at tool box safety meetings, obtain a signed receipt from each employee. This will help establish at the hearing that you adequately communicated the rule to employees.

Raytheon demonstrated its efforts to discover and correct violations of its safety rules by having its safety manager conduct safety compliance inspections several times each day. It is not enough to say that these inspections were made on a regular basis. In order to persuade the Judge, the contractor should have contemporaneous written business records such as a separate portion of the daily report, indicating that the daily safety inspections were made. Testimony unsupported by written records tends not to be persuasive at the hearings.

Lastly, the employer must prove that it effectively enforced the safety rules when violations were discovered. Raytheon met that burden by showing that it had in place a progressive disciplinary plan with increasingly harsh measures taken for infractions of the work rule. It was able to produce at the hearing, copies of three letters written at various times to employees concerning their violation of the work rule in question, which was a requirement that welder’s helpers wear eye protection. Additionally, Raytheon’s safety director showed that he had terminated an employee in the past for a safety rule violation Without enforcement, the unpreventable employee misconduct defense will fail.

In conclusion, when the facts establish that an OSHA standard was violated, an employer may still have a valid and effective defense against the citation when that violation was the result of an employee’s misconduct.

Contracting For Public Works Projects

Many facets of contracting for public works projects are controlled by statute. However, as in any area of the law, in order to determine how the satutes are applied and how much latitude a public entity has in bidding, awarding and administering the performance of public works contracts, it is important to refer to the decisions and opinions of our courts. The purpose of this article is to not only review some of the more important cases in this area, but to discuss the practical, philosophical and legal issues involved in public construction projects from bid phase to project close-out.

I. PUBLIC BIDDING

A. Project Specifications

Once the construction drawings and specifications are prepared, the project architect or engineer usually places an advertisement with the Dodge Reports or other publications to alert potential bidders so that they might pick up a copy of the plans and specifications and submit bids to perform the work. The project specifications contain an “invitation to bidders” which establishes the legal framework upon which the bidder submits its bid. The municipal owner, as financial security, will require the bidder to submit a bid bond. Should the low bidder refuse to accept the award of the contract, the surety on the bid bond is liable for the difference between the bidder’s bid and the next lowest bid up to the penal sum of the bond. The bidder remains responsible for any shortfall. In addition, after the bidder returns the executed contract, it will be required to submit a performance bond and labor and material payment bond to the municipality (State Finance Law ¬ß137). The performance bond acts as security for the public owner in the event the contractor fails to complete its work. In such an event, the surety has various options and may hire a contractor to complete the work left undone by the defaulting contractor. If the contractor is not sufficiently progressing its work, the owner may default the contractor. Determining whether or not to default a contractor is a very difficult decision for any municipal owner and should only be taken with the advice of counsel and careful consideration of the economic implications.

The labor and material payment bond acts as financial security for entities that furnish labor and material to the project. A public owner should be alert to payment bond claims being made as it may be a symptom that the contractor is not timely paying its subcontractors and suppliers. Payment bond claims also may work to reduce the protection the owner is afforded by the performance bond as most labor and material payment bonds and performance bonds have a joint penal sum so that if the surety pays a payment bond claimant the penal sum of the performance bond is reduced so that less protection is available for the owner to secure the completion of the project should the contractor default.

B. Competitive Bidding Statutes

Municipal owners, with certain exceptions, must award contracts to the lowest responsible bidder. Public bidding in New York is governed, by and large, by General Municipal Law ¬ß103. The General Municipal Law requires that the public owner award the contract to the lowest responsible bidder. In order to be the lowest responsible bidder, however, the bidder’s bid must be responsive. In other words, the bid must provide a price quote for every item for which the owner solicited a bid. If a bidder fails to submit a bid for a particular item of work, the bidder’s bid should be deemed “non-responsive” by the municipality. As a non-responsive bidder, the bidder should not be awarded the contract. A contract that is awarded in non-compliance with General Municipal Law √Ǭß103 is void so that the contractor would be performing its work at the risk of not having an enforceable legal right to be paid; the municipality would have the risk of the next lowest responsible bidder seeking court intervention to review the conduct of the municipality in awarding the contract. The next lowest bidder would, no doubt, ask the court to issue a temporary restraining order preventing the work from proceeding until meaningful court review could occur.

A municipality may set forth in its request for bids, certain minimum experience requirements for bidders on public contracts. For example, for a roofing project, the municipality may require bidders to demonstrate that they have “in the last five (5) consecutive years prior to the bid opening, successfully completed in a timely fashion at least two (2) roofing projects similar in type and scope to the work required under the contract bid upon, which projects must be completed and be in service for a minimum of two (2) full years prior to the bid opening. See, P&C Giampilis Construction Corp. v. William J. Diamond, et al., 619 N.Y.S.2d 271 (A.D., 1st Dept., 1994). In Giampilis, the Court held that the City of New York was not only entitled to reject the low bid since the low bidder failed to meet the experience requirements, it further determined that the municipality had a rational basis for rejecting the low bid, even though the principals of the corporate low bidder could demonstrate the requisite experience (i.e., the bid documents required the corporate bidder to have the requisite experience). The courts of this state have repeatedly upheld the rejection by municipal agencies of competitive bids, without any further investigation other than a review of the bid documents, based on non-responsiveness, where the bids failed to “comply with the literal requirements of the bid specifications”. See LeCesse Bros. Contracting, Inc. v. The Town Board of the Town of Williamson, 62 A.D.2d 28, 31, 403 N.Y.S.2d , 950, Affirmed 46 N.Y. 960, 415 N.Y.S.2d 413 (1978); A.I. Smith of Long Island v. The City of Long Beach, 158 A.D.2d 454, 551 N.Y.S.2d 48 [wherein the court upheld the City’s rejection of a bid for failure to include a “detailed declaration of the bidders qualifications” including the firm’s experience.] See also In re: Kaelber, 281 A.D. 980, 120 N.Y.S.2nd 556 (A.D., 2 Dept., 1953) and W.J. Gaskell, Inc. v. William J. Maslanka, Mayor of the Village of Garden City, 33 Misc.2d 88 225 N.Y.S.2d 94 (Nassau Co., 1962).

However, a public agency can go too far. In the Matter of Construction Contractors Association of the Hudson Valley, Inc., et al. v. Board of Trustees, Orange County Community College, et al., 192 A.D.2d 265, 600 N.Y.S.2d 953 (2nd Dept., 1993), the Court held that a requirement in the bid specifications for restoration work on a historic building located at Orange County Community College violated public bidding statutes because it was too restrictive and unreasonably limited the potential pool of bidders. The requirement was that the contractor must have successfully completed two restoration projects on buildings listed on the National Register of Historic Places within the previous five years. While the Court held that the successful completion of similar projects is a reasonable requirement, there was no evidence before the Court that buildings registered on the National Register of Historic Places presented restoration problems unlike those of other historical buildings which are not so listed. Therefore, the Court concluded that such a flat requirement does not pass muster under General Municipal Law §103.

A “responsible” bidder is one that does not have a record that would bare on their honesty, trustworthiness or their ability to complete the project, including the requisite experience for the particular type of work involved. In determining whether or not a bidder is the lowest responsible bidder, the municipal entity is vested with a certain measure of discretion. Should the bidder not receive the award of a contract to which it felt itself entitled, the bidder would then have to bring a special court proceeding under Article 78 of New York’s Civil Practice Law and Rules, seeking judicial review pursuant to which the court would determine whether the public entity “abused its discretion” or acted in an “arbitrary” or “capricious” manner. The standard of review of an agency’s decision to award or deny a contract is whether there is a rational basis to support that determination, and the burden of proving that there is no rational basis for the decision is on the contractor. (See Matter of Schiavone Construction Co. v. LaRocca, 117 A.D.2d 440, 444, 503 N.Y.S.2d 196, Lv. denied 68 N.Y.2d 610, 508 N.Y.S.2d 1026, (1986).

The courts have also recognized, however, that when a low bidder has its bid rejected with the inevitable implication of non-responsibility, its “commercial good name, reputation, honor, or integrity” is at stake. See LaCorte Electrical Construction and Maintenance, Inc. v. County of Rensselaer, 80 N.Y.2d 232, 590 N.Y.S.2d 26 (Court of Appeals of New York, 1992) citing Board of Regents v. Roth, 408 U.S. 564, 92 S. Ct. 2701, and Wisconsin v. Constantineau, 400 U.S. 433, 91 S. Ct. 507. While safeguards of reasonable notice and timely opportunity to be heard become operative in such circumstances, the public fisc and process must also be weighed in light of the additional expense of a more costly contract flowing from the rejection of the lowest bid. In considering the required and appropriate remedies for failure to afford necessary protections, courts are not blind to the need that governmental agencies be able to conduct business in an efficient and effective manner and to the potentially crippling effect that might result from the imposition of stringent due process requirements with respect to all government actions adverse to unsuccessful bidders on Government contracts. See, LaCorte Electrical Construction and Maintenance, Inc. v. County of Rensselaer, supra. While a low bidder does not acquire a property right in a contract, it has been held that a low bidder does have a “liberty” interest which includes the right to contract. See LaCorte Electrical Construction and Maintenance, Inc. v. County of Rensselaer, supra. As a result, there are certain minimal due process requirements which the municipality must meet when making a determination that a contractor is not a “responsible bidder”. Giving the bidder notice of a municipality’s concern over its responsibility and the reasons for that concern, and affording the bidder the opportunity to rebut the charges both in writing and at informal hearings have been determined to meet the minimal due process requirements, especially in light of the availability of court review pursuant to CPLR Article 78. See Matter of Schiavone Construction Co. v. LaRocca., supra. It is important to note that in reaching a determination of non-responsibility, it is not necessary for the municipality or agency to have an evidentiary hearing, as long as there is an opportunity for the low bidder to be heard whether at a meeting or in the form of written submissions. See Tully Construction Co., Inc. v. Hevesi, 214 A.D.2d 465, 625 N.Y.S.2d 531 (A.D., 1st Dept., 1995).

The owner, in determining which bidder is the lowest responsible bidder, should check the bidders references to make sure that the bidder is “responsible”. The owner should also review the bid with the bidder to make sure that the bidder has a complete understanding of the scope of work to be performed.

Municipal owners should also be wary of prime contractors acting as brokers and not actually performing any work activities themselves. In order to guard against this risk, the contract should have a limitation on the dollar value that can be subcontracted. Certain public entities also establish Minority and Women owned Business Enterprise (“MBE” and “WBE”) goals that are typically met by subcontracting certain aspects of work.

Upon determination of the apparent lowest responsive and responsible bidder and prior to award, the municipality or agency may elect to open negotiations with the selected bidder in an effort to improve the bid to the municipality or agency with respect to the price only. In Matter of Fischbach & Moore v. New York City Trataros. Auth., 79 A.D.2d 14, 435 N.Y.S.2d 984,(2nd Dept., 1981) lv. denied 53 N.Y.2d 604, 439 N.Y.S.2d 1028 (N.Y., 1981), the court held that once the bidding process fairly produces a lowest responsible bidder, there is no supervening interest or policy consideration which precludes a municipality or agency from negotiating and obtaining a post bid, pre-award price concession from that very same bidder. However, the court cautioned that a municipality may not “engage in post-bid negotiations through which a contractor other than the low bidder may become the low bidder, or coerce a low bidder to making unfair and unwarranted concessions through the threat of rejecting all bids. In the event the apparent lowest responsive and responsible bidder declines to negotiate, the municipality may elect to either award the contract to the apparent lowest responsive and responsible bidder or may, upon reasonable grounds, reject all bids in accordance with General Municipal Law √Ǭß103. See also, Acme Bus Corp. v. Board of Education of the Roosevelt Union Free School District, 91 N.Y.2d 51, 666 N.Y.S.2d 996 (1997).

It is important to recognize that the laws requiring competitive bidding were designed to benefit tax payers rather than corporate bidders, and, thus should be “construed and administered with sole reference to the public interest”. See, Acme Bus Corp. v. Board of Education of Roosevelt Union Free School District, supra. In Matter of New York State Ch., Inc., Associated Gen. Contrs. V. New York State Thruway Auth., 88 N.Y.2d 56, 643 N.Y.S.2d 480, 666 N.E.2d 185, the New York Court of Appeals declared that there are:

“two central purposes of New York’s competitive bidding statutes, both falling under the rubric of promoting the public interest: (1) protection of the public fisc by obtaining the best work at the lowest possible price; and (2) prevention of favoritism, improvidence, fraud and corruption in the awarding of public contracts.”

In Acme Bus Corp. v. Board of Education of Roosevelt Union Free School District, supra, the court stated that these separate goals are not incompatible. Favoritism or irregularity in the bidding process may ostensibly produce monetary savings, but the use of such means to meet that singular end is still unsustainable because the complete public interest is ultimately promoted by fostering honest competition. The spectral appearance, however, of impropriety is insufficient proof to disturb a board’s determination under the competitive bidding statutes. An unsuccessful bidder has the burden to demonstrate “actual” impropriety, unfair dealing or some other violation of statutory requirements when challenging an award of a public contract. See Matter of Conduit & Found. Corp. v. Metropolitan Transp. Auth., 66 N.Y.2d 144, 495 N.Y.S.2d 340 (N.Y.,1985).

A public owner issues an award of contract to the bidder it deems to be the lowest responsible bidder and then issues a “Notice of Award” and ultimately a “Notice to Proceed” when the work is ready to commence. Upon the bidder’s receipt of the Notice of Award, the bidder will be required to return the executed contract and forward the appropriate bonds and insurance certificates. After the owner receives and reviews the executed contract and makes sure that the necessary bonds and insurances have been provided, the owner will then issue a Notice to Proceed directing the bidder, now contractor, to start work.

C. Bid Mistakes

On occasion, a bidder may submit a bid that is disproportionately low when compared with with the owner’s estimate of the costs, or the bids submitted by other bidders. In such a case, the owner may be on notice that the bidder made a mistake. The bidder may also realize that it made a mistake and seek to withdraw its bid. The owner when faced with deciding whether or not to permit a bidder to withdraw its bid, must act with a high degree of caution as the municipality, bidder and its surety as well as the next lowest bidder all have a financial stake in the decision. In order for a municipal owner to legally accept the withdrawal of a bid based on a mistake, it must first receive a notice from the bidder within three days of the bid opening requesting the withdrawal of its bid. General Municipal Law √Ǭß103 (11)(a), states as follows:

11. Bid mistakes; public projects. (a) In all contracts governed by this section, where a unilateral error or mistake is discovered in a bid, such bid may be withdrawn after a showing of the following: (1) the mistake is known or made known to the awarding officer, board or agency prior to the awarding of the contract or within three days after the opening of the bid, whichever period is shorter; and (2) the price bid was based on an error of such magnitude that enforcement would be unconscionable; and (3) the bid was submitted in good faith and the bidder submits credible evidence that the mistake was a clerical error as opposed to a judgment error; and (4) the error in the bid is actually due to an unintentional and substantial arithmetic error or an unintentional omission of a substantial quantity of work, labor, material, goods or services made directly in the compilation of the bid, which unintentional arithmetic error or unintentional omission can be clearly shown by objective evidence drawn from inspection of the original work paper, documents, or materials used in the preparation of the bid sought to be withdrawn; and (5) it is possible to place the public agency, board, officer, or subdivision in status quo ante.

Upon the owner’s receipt of such a letter from a bidder, the owner should carefully review the supporting documentation to make sure that the error was a clerical error and not an error in judgment. An error in judgment is not a sufficient basis for accepting the withdrawal of a bid.

For example, an agency’s refusal to permit a contractor to withdraw its bid was found not to be arbitrary or capricious where shortly after the bid was accepted, the contractor notified the agency that it had made an error, but delayed three months before requesting to be released from its bid. Gilston Elec. Contracting Corp. v. Popolizio 169 A.D.2d 583, 564 N.Y.S.2d 435 (1st Dept., 1991). In Balaban-Gordon Co. v. Brighton Sewer Dist. No. 2, 67 Misc.2d 76, 323 N.Y.S.2d 724 (Sup. Ct., 1971), the court held that where a contractor prepared a bid for general construction for a sewage treatment plant, and also a bid for the plumbing and equipment for such plants, and in doing so, misinterpreted the specifications and erroneously omitted certain items that had to be furnished under the general construction contract computations it made in preparing its bid for such contract and instead included these items in computations it made in preparing its bid for the plumbing contract, and contractor gave sewer district notice of mistake the day after bids were opened, the district could not properly retain advantage of the contractor’s mistake, and fair dealing required that contractor be relieved of its bid.

II CONTRACT PERFORMANCE AND CLAIMS

A. Role of Project Architect as Owner’s Representative

After the award of the contract and Notice to Proceed is issued, the architect or consulting engineer will typically act as the owner’s representative during the course of construction. The owner’s representative will coordinate the kick-off meeting and schedule weekly progress meetings or such other meetings as are necessary to monitor the work performed by the contractors. The owner’s representative does not insure the quality of the work, but instead acts as the owner’s eyes and ears to make sure that the work is being performed in accordance with the contract specifications.

The main role served by the owner’s representative is to certify what payments are properly due and owing the contractors. Contractors typically submit requisitions for payment on a monthly basis whereupon the owner’s representative reviews the requisition with the contractor at the project site to determine what percentage of completion was achieved by the contractor. The contract is typically divided into items of work so that the contractor submits a “schedule of values” for each item of work. After the owner issues a Notice of Award, the owner’s representative and the bidder will agree upon what values should be attributed to each item of work and a schedule of values is prepared.

Some contracts are awarded on a lump sum basis while others are on a unit price basis depending on the nature of the work involved. Regardless of the manner in which the contractor is to be compensated, the owner’s representative will monitor the level of completion and certify what payments are due.

B. Interpretation of Contract

The owner’s representative, during construction, typically acts as the first interpreter of contractual disputes so that if a contractor submits a request for a change order seeking additional money for certain work, the owner’s representative will review the plans and specifications and make a recommendation to the owner as to whether or not a change order should be issued. Owners should be careful to document any disagreements it may have with its architect concerning whether or not any item of given work is additional work, because the contractor could, in a subsequent lawsuit, claim that the architect was not exhibiting independent professional judgment or that the owner and the architect conspired to deprive the contractor of its working capital.

C. Presentation of Claims

The owner’s representative, in addition to making various determinations as to whether or not a contractor is entitled to be issued a change order for additional work, must also determine whether a contractor should be granted an extension of time to perform any additional work or in order to compensate the contractor for unanticipated delays it encountered in performing its work. The owner should be careful in this area and should seek legal counsel as disclaimers may or may not protect the owner depending on the circumstances. Early resolution of a contractor’s claim will, in the long run, limit the owner’s costs.

Certain disclaimers and other legal clauses can protect a municipality from liability depending on the circumstances. For example, to avoid responsibility for incorrect or incomplete information, bid documents often include disclaimer clauses, which generally require the contractor to investigate the project site and determine the risks associated with building the project. The owner also typically disclaims responsibility for the information it provides and states that such information is provided for estimating purposes only. An effective disclaimer prevents the contractor from claiming that it reasonably relied on the accuracy of certain bid information and requires the contractor to make its own investigations.

Disclaimer clauses, however, are strictly construed against owners. Changed conditions clauses are also often used in municipal contracts. Such a clause provides for procedures for identifying changed conditions and modifying the contract if additional work is necessary due to unanticipated conditions. An example of such a clause follows:

Viewing of Site and Consideration of Other Sources of Information (b) Changed Conditions – Should the contractor encounter during the progress of the work, subsurface conditions at the site materially deferring from any shown on the Contract Drawings or indicated in the specifications or such subsurface conditions as could not reasonably have been anticipated by the contractor and were not anticipated by the City, which conditions will materially effect the cost of the work to be done on the contract, the attention of the Commissioner must be called immediately to such conditions before they are disturbed. The Commissioner shall thereupon promptly investigate the conditions. If he finds [a changed condition]. . . the contract may be modified . . .(Andrew Catapano Co. v. City of New York, 116 Misc.2d 163, 455 N.Y.S.2d 144 (S. Ct., 1980).

A common exculpatory clause found in municipal contracts is what is known as the “No Damage for Delay” clause. Such a clause attempts to excuse an owner from contractual liability for monetary damages due to delays caused by itself, its architect and/or engineer and other entities under its employ. While “no damage for delay” clauses are generally valid and enforceable in New York, the courts have carved out certain exceptions. See Corinno Civetta Construction Corp. v. City of New York, 67 N.Y.2d 297, 502 N.Y.S.2d 681 (NY Ct. of Appeals, 1986). Generally, even with such a clause, the contractor may recover damages for: (1) delays caused by the contractee’s bad faith or its willful, malicious, or grossly negligent conduct; (2) uncontemplated delays; (3) delays so unreasonable that they constitute an intentional abandonment of the contract by the contractee; and (4) delays resulting from the contractee’s breach of a fundamental obligation of the contract. See Corinno Civetta Construction Corp. v. City of New York, supra.

In a recent case, the Supreme Court of the State of New York, Appellate Division, Third Department, held that a contractor on a school renovation project was entitled to recover delay damages against the school district even though the public contract contained a “no damage for delay” clause. See, Clifford R. Gray, Inc. v. City School District of Albany, 2000 N.Y. Slip Op. 10376, 2000 WL 1742731. The Court found that: (i) the evidence was sufficient to support a determination that the delays were uncontemplated; and (ii) the school district was responsible for the breach of fundamental contractual obligations, permitting the contractor to recover its delay damages despite the contract’s exculpatory clause.

Contract clauses conta

Protecting The Rights Of Subcontractors And Suppliers Under New York State Law

The following information is intended as general guidance on how subcontractors and suppliers can secure and receive payments that are due. There are four main methods for obtaining security and enforcing payment obligations in New York State.

1. The Mechanic’s Lien Law. The two broad categories are a public lien and private lien. The determination of which type of lien to is appropriate to file depends on ownership of the subject real property and the source of funding for the project.

A. Public Lien. A public lien must be filed within thirty days after final completion of the project is achieved. This time limit does not depend on when a subcontractor performs its work or when a supplier delivers its materials to the project. Instead, the period of time within which the lien must be filed is measured from final completion of the entire project. Some public agencies issue certificates of final completion so that this time frame can be determined.  Most often, as long as the public funds have not been fully dispersed the lien will attach. 

B. Private Lien. A private lien must be filed within four months of last performing work or delivering materials to a project if the project is a residence or within eight months if the project is commercial in nature.

A private lien has a duration of one year from the date of filing and can be extended for an additional one year by the filing of a notice of extension of the lien, except for single family residences which require a court order to be extended.

In either case, before the expiration of the lien, a mechanic’s lien foreclosure action must be commenced in order to preserve the lien. The mechanic’s lien foreclosure action requires a summons and complaint be filed and served. Typically, a notice of pendency also must be filed.

It is important to recognize that a lien acts only as security for an underlying contractual or quasi-contractual debt. Although a lien can be filed for the full amount due, it is only enforceable to the extent that moneys are due and owing “upstream” to the party against whom the lien is claimed. If, for example, a general contractor has back charges, even if completely unrelated to the materials the supplier delivered to its subcontractor, the supplier’s right to enforce its mechanics’ lien are reduced. Even if a lien is unenforceable, subcontractors and suppliers can still maintain a breach of contract action directly against the party with whom they contracted. The derivative nature of a mechanic’s lien makes it important to file a lien as soon as possible. The filing of a lien typically results in the owner and/or general contractor withholding payments “down stream”. Consequently, the prompt filing of a lien will usually result in greater funds against which the lien can attach and be enforced.

Additional devices to consider in the mechanic’s lien area include a demand for terms of contract and a demand for a verified statement. The demand for terms of contract, if not responded to within thirty days, can create direct liability on the part of a remote party if the claimant cannot collect against the party with whom it contracted. The demand for a verified statement will be discussed below.

2. Payment Bond Claims. Independent of mechanic’s lien rights, subcontractors and suppliers should be conscious of the possibility of a payment bond existing. The larger the job the more likely a payment bond exists. Also note, nearly all public jobs require payment bonds. A typical payment bond requires suppliers (but not subcontractors in direct contract with the prime contractor) to provide written notice, sent by certified mail, return receipt requested, to all parties “upstream” within ninety days of last supplying materials to the subject project. Bond terms vary, but ninety days is typical.

The payment bond claim should include the name of the project, the contractual relationships (i.e., owner, general contractor and subcontractor, etc.), and the amount owed.

A payment bond claim can be made even if the name of the surety is not known. All that is required is that written notice be sent certified mail, return receipt requested within the appropriate period of time to the owner and contractor (i.e., the principal on the bond). Some bonds excuse the written notice requirement if the bond claimant has a direct contract with the principal on the bond. Unless the bond terms are known, it is best to send the written notice to all interested parties.

Bonds typically have two time limits. First, a written notice requirement such as the one detailed above acts a condition precedent to a bond claim. And second, a period of limitations requirement usually exists which requires that any lawsuit on the bond be commenced within a certain period of time. The typical time limitation to commence a lawsuit is one year from the last day worked or the last day materials are supplied to a particular project.

A supplier’s payment bond claim is enforceable against the bonding company regardless of whether or not the general contractor (the principal on the bond) has paid its subcontractor in full. Thus, the inherent limitation on the enforceability of liens (i.e., derivative rights) is not an obstacle to the enforcement of a payment bond claim. Accordingly, a payment bond claim is of greater value than a lien because it provides greater security for payment if it can be proven that work was performed or deliveries of materials occurred.

Note: In the case of either a mechanic’s lien or a payment bond claim, it is critical to prove that moneys are due under a contract, etc. For suppliers, proof that materials were actually delivered to a particular job is needed. Accordingly, approved requisitions for payment, signed delivery tickets showing the name of the project, etc., are important proof of the amount due. Suppliers, if possible, should avoid shipments to a customer’s warehouse, as lien and bond rights may be limited in such a case.

3. Trust Fund Diversion Claims. Article 3-A of the New York State Lien Law, which operates completely independent of the mechanic’s lien law itself, has the potential to create personal liability on the part of the officers of the contractor if a corporation. Contractors are duty bound to make sure that moneys intended for the costs of improvement on a given project are used to first to pay those that actually improve the project. If a general contractor pays a subcontractor and the subcontractor pays, for example, a supplier from another job (or goes on vacation to Italy), the officers of the subcontractor could be personally liable. The first step to create liability is to serve a demand for a verified statement which demands information, under oath, as to the application of the funds received upstream.

4. Personal Guaranty. Credit applications and contracts may provide for a personal guaranty so that a direct action and/or arbitration against the individual guarantor can be maintained. There are expedited procedures available in court when a lawsuit is based on a personal guaranty.

The best way for subcontractors and suppliers to enforce payment rights is to be conscious of their lien and payment bond rights, which act as security for contractual and quasi-contractual debts. Merely filing a mechanic’s lien and making a payment bond claim will not typically result in payment. Sureties as a rule do not voluntarily pay claims and an owner or contractor will likewise not pay until the subcontractor and/or supplier “judicially” establishes its right to payment. While it is important to file a lien and/or make a payment bond claim for security purposes, it is equally important to speedily obtain a judgment or arbitrator’s award. The time within which a recovery can be had depend on numerous factors, the most important of which is the claimant’s ability to clearly document the amount owed.

Various legislative initiatives like the New York Prompt Payment Act should also be considered as possible tools to expedite payments.

Subcontractors and suppliers should consult with counsel as soon as it become apparent that a payment risk exists as the information contained in this article is intended as general guidance only.

Defending Against An OSHA Citation: A General Contractor’s Perspective

General Contractors have a dual concern when it comes to protecting their companies from OSHA citations: they must not only be on guard against OSHA violations committed by their own employees, but a prudent General Contractor should also be vigilant with respect to a subcontractor’s employees whose violative acts will often be imputed by OSHA to the General Contractor because of the General Contractor’s control over a site. It is particularly difficult for a general contractor to protect itself against violations caused by independent acts and omissions of employees and subcontractors of which the General Contractor has no knowledge. For these reasons, there are a series of steps which every General Contractor should consider taking in order to protect their companies from OSHA citations in such instances.

In general, applicable OSHA case law has held that an employer cannot be held responsible for the violation of an OSHA standard resulting from an act by an employee (and by analogy, a subcontractor), for which the employer ( or General Contractor) has no knowledge and which was contrary to the employer’s instructions. In order to establish this defense, known as “unpreventable employee misconduct,” the employer must demonstrate the following:

(1) the violation must have been caused by or resulted from exclusively employee action; (2) it must have been an isolated and unanticipated instance; (3) it must have been of short duration; (4) it must not have been participated in, observed by, or performed with the knowledge of supervisory personnel and must not have been foreseen by the employer in the exercise of reasonable diligence; and (5) the employee’s action was in contravention of well established policy, program or rule which was used to instruct employees in safe work practices and which was enforced by disciplinary action when necessary.

Therefore, with respect to employees, a General Contractor should have in place a well established written company-wide safety plan covering all aspects of the contractor’s operations, including both management and employees. Having the safety plan reviewed by an independent consultant, and then implementing any suggestions made by that consultant further strengthens the safety plan.

Next, elements of the company-wide safety plan need to be communicated to the employees by whatever means possible, including at “tool box meetings”. For example, a General Contractor should consider covering a different topic of workplace safety each week at “tool box meetings”, and at those meetings, handing out pamphlets and literature to the employees regarding various topical OSHA rules. Employee attendance at those meetings should be documented.

Finally, the safety plan needs to be actively enforced by the General Contractor, including reprimanding and dismissing employees that disregard explicit safety rules. Enforcement should similarly be documented with memos, letters and other employment records.

With respect to subcontractors, by analogy, the Contractor should have a written company-wide safety plan describing how the General Contractor communicates and enforces safety issues with subcontractors, including the use of comprehensive contract clauses concerning workplace safety. It should be made clear that a breach of OSHA rules is a breach of the subcontract and the failure to cure could, as with any material breach, be grounds for termination.

During the course of the project, those safety issues need to be effectively communicated to the subcontractors at project meetings and later confirmed in meeting minutes. Correspondence and field memos should also memorialize the communication of safety concerns. For example, the site superintendent should immediately notify a subcontractor in writing when he or she witnesses an unsafe situation and the superintendent should then follow-up on those notifications.

Finally, safety issues should be actively enforced with the subcontractors through various contractual mechanisms, including withholding funds, threatening termination, and even terminating recalcitrant subcontractors when the circumstances warrant it.

In the event a General Contractor is issued a citation by OSHA resulting from the independent act of an employee or a subcontractor, documentation of the aforementioned steps could prove in valuable in defending against the citation at an informal conference or a full hearing.

Strict Compliance With Notice And Reporting Provisions

A 1998 decision by the State of New York’s highest court underscores the importance of contractors strictly complying with the notice and reporting provisions contained in many construction contracts, no matter what type of “directive” they may have received from the Owner or its representatives.

In A.H.A. General Construction, Inc. v. New York City Housing Authority, 92 N.Y.2d 20, 677 N.Y.S. 2d 9 (June 11, 1998), the Court of Appeals of New York dealt with a common scenario on construction projects. According to the contractor, the public owner would, during the course of the project (as was the case on their previous projects), direct the contractor to perform extra work and the work would then be done with the expectation that a change order would be issued or that correspondence containing price proposals submitted by the contractor to the Owner would constitute sufficient notice and documentation of its claim. The contractor claimed that the parties would negotiate over claimed extra work and ultimately the contractor would be paid for same.

The public owner, however, had a different recollection. It denied the contractor’s contention that, with respect to work that the public owner claimed was contract work but the contractor contended was extra, the public owner permitted the contractor to use correspondence as a substitute for the documentation required by the contract. The public owner argued that by the express terms of the contract, only when both parties agreed that an item of work was extra and when prior to the performance of the work, the public owner ordered the contractor in writing to perform the work for an agreed upon sum, would the contractor’s obligation to submit daily reports be obviated.

By the end of the project, several disputes arose over whether the work performed by the contractor was extra work, or work required under the contract. On some occasions, the public owner issued the requested change order, on others it refused, and on still others, it issued change orders only to subsequently rescind them.

The contractor commenced an action against the public owner alleging claims of breach of contract and unjust enrichment and the public owner moved for summary judgment dismissing the complaint, on the grounds that the contractor had waived its right to recover for extra work by failing to comply with the notice and reporting requirements of the contract.

The contractor’s president in opposing the public owner’s motion for summary judgment, swore in his affidavit that the public owner was “being less than truthful” and was “acting in bad faith” by suggesting that no documentation existed to support the contractor’s claims for extra work. The contractor noted the vast amount of correspondence between the parties on that issue, including requests by the public owner to complete certain tasks, and the contractor’s detailed cost proposals responding to those requests. The contractor’s president further stated that certified payroll reports and daily activity reports were kept regarding all of the work but that separate records for the extra work could not be kept because it was physically impossible to do so.

The lower court ruled that no matter how much correspondence existed on the issue, and how many project records existed, the contractor’s failure to strictly comply with the contract’s notice and reporting requirements(1) barred it from recovering for the extra work.

On appeal, the contractor argued that the public owner’s actions waived strict compliance with the notice and reporting provisions because of the hundreds of instances in the past where it had negotiated payment for extra work without requiring technical compliance with those provisions. This argument, coupled with the evidence that the public owner had also executed change orders acknowledging that certain work was extra work only later to rescind them, asserting that the work was actually required by the contract, was enough to sway the State of New York’s Appellate Division, First Department to find that the contractor had raised triable issues of fact as to whether the public owner had acted in bad faith or had been grossly negligent in the performance of the Contract.

The Appellate Division’s decision, however, was short lived because the New York City Housing Authority took its appeal up to New York’s Court of Appeals. The Court of Appeals reversed the Appellate Division and upheld the decision of the lower court finding that the contractor had failed to come forward with any evidence to demonstrate that the actions of the public owner had in any way prevented him from complying with the strict notice and reporting requirements contained in the contract. The Court determined that the applicable provisions of the contract required the contractor, when proceeding with disputed work, to submit contemporaneous statements and documentation of its actual damages, not proposed costs or estimates. The Court of Appeals also specifically found that the public owner’s own daily construction site reports and the contractor’s submission of certified payroll reports – neither differentiating between contract work and disputed work – did not satisfy those requirements.

The Court of Appeals’ reversal of the Appellate Division’s decision rested on its conclusion that the notice and reporting provisions of the contract were “conditions precedent” to suit or recovery for the extra work, and not “exculpatory clauses”.(2) The Court said:

That conclusion is legally significant. While an exculpatory clause will not be enforced when, “in contravention of acceptable notions of morality, the misconduct for which it would grant immunity smacks of intentional wrongdoing” (Kalisch-Jarcho, Inc. v. City of New York, 58 N.Y.2d at 385, 461 N.Y.S. 2d 746, 448 N.E. 2d 413, supra), the standard for excusing a condition precedent is different. A condition precedent is linked to the implied obligation of a party not to “do anything which will have the effect of destroying or injuring the right of the other party to receive the fruits of the contract” (Kirke La Shelle Co. v. Armstrong Co., 263 N.Y. 79, 87, 188 N.E. 163). Thus, it is a “well-settled and salutary rule that a party cannot insist upon a condition precedent, when its non-performance has been caused by himself” (Young v. Hunter, 6 N.Y. 203, 207; see also Arc Elec. Constr. Co. v. Fuller Co., 24 N.Y.2d 99, 104, 299, N.Y.S. 2d 129, 247 N.E.2d 111; 3A Corbin, Contracts 767, at 540 [1960]). Put another way, a party to a contract “cannot rely on the failure of another to perform a condition precedent where he has frustrated or prevented the occurrence of the condition” (Kooleraire Serv. & Installation Corp. v. Board of Educ., 28 N.Y.2d 101, 106, 320 N.Y.S.2d 46, 268, N.E.2d 782; see also, Armies v. Wesnofske, 255 N.Y. 156, 163, 174, N.E. 436; Patterson v. Meyerhofer, 204 N.Y. 96, 100-101, 97 N.E. 472).

Therefore, New York’s Highest Court determined that the relevant inquiry is not simply whether the Owner committed bad faith or was negligent in the performance of the contract, but whether the alleged misconduct prevented or hindered the contractor’s compliance with the notice and reporting requirements. The Court ultimately decided in the case before it that none of the actions attributed to the Owner by the contractor impeded the contractor’s ability to comply with the contract requirements as to its claims of extra work, and the contractor’s complaint was dismissed.

The moral of the this saga is that every contractor or subcontractor faced with a contract containing notice and reporting provisions covering the performance of extra work or disputed work must not only give notice to the Owner but must also strictly comply with the reporting provisions while the work is being performed (e.g. submit daily time and material records for the Owner’s signature). This must be done even if you are promised a change order, directed to proceed in writing, or in the midst of negotiating a change order. If the extra work is completed without a signed change order and without complying with the contract’s reporting provisions, the contractor will be completely at the mercy of the owner and will, in all likelihood, lose its claim no matter how clear cut the issue may be.

A.H.A. General Construction, Inc. waived its rights to approximately $1 million in claimed extras by failing to follow the express terms of the contract. Don’t let it happen to you.

1. The subject contract required that in the event the Owner determines that the work being performed is not extra work, the contractor must notify the Owner within 5 days that the work is being performed “under protest”, or else the claim for extra work is waived. Also, a contractor claiming damages resulting from an act or omission of the Owner is required to give notice within 5 days of the act or omission, and provide detailed statements and proof of damages within 30 days, or the claim would also be waived.

Under another section of the contract, a contractor performing extra work or disputed work is required to furnish daily statements to the public owner, during the performance of that work, including the names and number of workmen employed on the work; the number of hours employed; the character of the work; and the nature and quantity of any materials or equipment used.

2. Exculpatory clauses like “no-damage-for-delay” clauses are meant to absolve or exculpate the Owner from liability for its acts or omissions.

The Construction Contracts Act

The Construction Contracts Act (hereinafter the “Act”) went into effect on January 14, 2003. All private construction contracts entered into after January 13, 2003, whether oral or written, where the aggregate amount of the construction project is $250,000.00 or more will be subject to the Act. Public works projects and contracts for the performance of work on public works projects are exempt from the Act’s provisions. In addition, certain residential projects and projects arising out of the events of September 11, 2001 are exempt from the Act.

The intent of the legislature in passing the Act was to prevent unjust delays in payments to contractors and subcontractors, working on private construction projects. If payments are not timely made, the Act establishes remedies for the benefit of contractors and subcontractors. The bulk of the Act’s provisions are triggered only upon default and can be bypassed if the construction contract is carefully drafted. However, the right to interest payments, the right to suspend performance and the right to have New York Law cover the rights of the parties and designating New York as the forum for any and all disputes are requirements for all contracts subject to the Act. Contracts with material suppliers are excluded and may be made subject to the laws of another State or jurisdiction and/or designate another jurisdiction or State as the venue for any and all contract disputes.

In the absence of an agreement to the contrary, the Act authorizes contractors and subcontractors to invoice for interim payments on a monthly basis. The party being invoiced, whether it is the owner, contractor or subcontractor, is required to approve or disapprove the invoice within twelve (12) business days of receipt of the invoice and all contractually required documentation, including partial waivers of lien. If the owner, contractor or subcontractor disapprove of the invoice or any portion thereof, it must prepare a written statement outlining the item(s) which are not approved, the reasons why and the amount(s) being withheld. The Act recites a list of grounds a party may raise when disapproving an invoice or any portion thereof. The sum of the withholdings are limited to amounts sufficient to cure and/or correct the defects and capped by the line item amount in the schedule of values, if previously submitted. In essence, the withholdings must be reasonable and can be based on contract provisions such as the owner’s and/or contractor’s rights to liquidated damages if the contract is not performed on time. However, the Act also provides that delays by anyone other than the invoicing party and/or its subcontractors and material suppliers shall not be a basis for withholding approval and payment of an application for payment.

Unless otherwise agreed, payments are due no later than thirty (30) days from approval. In situations involving subcontractors, payment is due, from the party with which it subcontracts, within seven days of that party’s receipt of good funds. Although not discussed here, the reader is also alerted to the fact that the Act contains provisions for situations when a lender is involved in financing all or part of the contract.

A contractor or subcontractor must disclose to a subcontractor of any tier the dates when payment is expected or contractually mandated from the owner or contractor. If the contractor or subcontractor fails to furnish the required notice, then it will be concluded that the due dates or time periods adopted by the act were complied with and payment will have to be made according to these adopted dates or time periods. Additionally, upon a written request from the subcontractor and within five (5) days of the request, the owner must provide the subcontractor with written notice of making any payments to the contractor.

Notwithstanding any agreements to the contrary, if payments are made beyond the due date, the party who owes the monies must pay interest at the rate of one percent (1%) per month or at a higher rate, if previously negotiated by the parties. In addition, the contractor may suspend performance without being in breach of the contract, if a ten (10) day written notice is provided to the owner with an opportunity to cure, and the notice outlines the contractor’s intention to suspend performance because payments were not timely approved or made. The subcontractor has the same remedy available to it when approvals and payments are unreasonably withheld, however, it must provide the ten (10) day written notice with an opportunity to cure to both the owner and contractor. The subcontractor may also suspend performance if the owner forwards payment to the contractor but the contractor fails to remit the payment to the subcontractor for its approved work.

In the event contractor or subcontractor suspends performance, the time frames established for performance are extended for the length of the suspension. The costs incurred for re-mobilization, however, can only be collected if negotiated by the parties. The Act provides that the suspending party must be permitted a reasonable opportunity to remove its materials, equipment, tools and/or machinery from the job-site.

If the parties agree, the Act permits retainage to be withheld, however, the contractor cannot retain an amount which exceeds the retainage withheld by the owner. Retainage must be released within thirty (30) days final approval of the work or interest will begin to accrue from the date the retainage became due and owing. The contractor must release proportionate amounts of retainage to each subcontractor after receipt of retainage from owner.

The definitions enumerated in the Act are very far-reaching, including how the terms “Construction Contract”, “Contractor”, “Subcontractor” and “Owner” are defined. The definitions, subject to the exemptions mentioned above, were intended to encompass most, if not all, contracting entities working on private construction projects greater than or equal to $250,000.00. Nevertheless, a carefully drafted contract can circumvent a majority of the Act’s more onerous provisions. Hopefully, the legislative intent of protecting contractors and subcontractors from unscrupulous payment practices will prevail. If you would like more information on this or any other construction issue, please feel free to contact Welby, Brady & Greenblatt, LLP.

This Article is supplied for informational purposes only and is not intended to constitute legal advice. You should consult competent legal counsel depending on the specific issues of your matter.

High Court K.O.’S Pay-If-Paid Clause

On December 7, 1995, the New York Court of Appeals, the highest Court in this State, handed-down a decision which changes the body of construction law and impacts the process of subcontracting. All CIC members, whether they are general contractors, subcontractors or suppliers, will be affected by the Court’s ruling.

In this landmark case entitled West-Fair Electric and L.J. Coppola, Inc. v. Aetna Casualty & Surety and Gilbane Building Company, the High Court held that:

“… a pay-when-paid provision which forces the subcontractor to assume the risk that the owner will fail to pay the general contractor is void and unenforceable as contrary to public policy set forth in the Lien Law Section 34. By contrast, a pay-when-paid provision which merely fixes a time for payment does not indefinitely suspend a subcontractor’s right to payment upon the failure of an owner to pay the general contractor and does not violate public policy as stated in the Lien Law.”

In essence, in the normal course of a construction project, slight delays in payment from an owner to a general contractor would permit a corresponding slight delay from the general contractor to the subcontractor or supplier, if the subcontract or purchase order contained a simple pay-when-paid clause. If, however, the subcontract or purchase order contained a clause stating that the general contractor’s obligation to pay the subcontractor was subject to the “condition precedent” of payment from the owner to the general contractor, a pay-if-paid clause, such a term will henceforth be legally void and unenforceable because its enforcement would run afoul of the public policy of the State of New York to protect subcontractors and suppliers. In so ruling, the Court of Appeals has overturned earlier decisions by New York’s intermediate appellate courts.

The lawsuit developed as a result of the financial failure of a project known as the Westchester Pavilion, a new mall resulting from the gut-rehab of the former Alexanders store in White Plains, New York. The owner/developer was Fischer-Reese; the general contractor/construction manager was Gilbane Building Company of Rhode Island and the architect/engineer was the Planned Expansion Group of White Plains. Several Construction Industry Council members were subcontractors to Gilbane on this project.

The cost of construction, approximately $23,000,000.00, greatly overran the original budget by approximately 62%. As a result, towards the end of the project, subcontractors and suppliers were owed millions of dollars which the owner could not pay. Mechanic’s liens were filed and bond claims were asserted.

Several of the subcontractors, including West-Fair Electric Contractors, Inc. and L.J. Coppola, Inc., were represented by Michael E. Greenblatt and Thomas H. Welby of CIC Associate Member Welby & Brady, LLP (formerly Welby & Welby), who commenced a mechanic’s lien foreclosure action against the property in State Supreme Court, Westchester County, and simultaneously, commenced a breach of contract and bond claim lawsuit in U.S. District Court. Gilbane and Aetna moved for summary judgment to dismiss the subcontractors’ lawsuit on the basis that the subcontract contained the following language: “It is specifically understood and agreed that the payment to the trade contractor is dependent, as a condition precedent, upon the construction manager receiving contract payments, including retainage from the owner…” West-Fair and Coppola cross-moved for summary judgment stating that the subcontractors had fully performed their work and that the operative language was not intended to shift credit risk to the subcontractors, particularly where their general contractor has posted a labor and material payment bond.

Hon. Charles L. Brieant held for the subcontractors stating that the position urged by Gilbane and Aetna violated the public policy of the State of New York, as stated in Section 34 of the Lien Law, which renders void and unenforceable, any contract provision which purports to waive a subcontractor’s right to file and/or enforce a mechanic’s lien.

The general contractor and the surety then appealed to the U.S. Court of Appeals for the Second Circuit. That Court determined that the central issue in the case turned on a matter of New York law on which New York’s highest court had never been called upon to decide. Therefore, the Second Circuit certified two questions of law to the New York Court of Appeals, which subsequently found for the subcontractors in the twelve page Decision and Opinion handed-down last week. The High Court’s Decision was unanimous.

The Court’s decision is both logical and fair in that it calls upon general contractors to be responsible for the financial risks that they, rather than the subcontractors and suppliers, stand in a better position to evaluate and manage. Needless to say, the Court’s lengthy Opinion, although resolving the central issue, leaves many questions unanswered. The full impact of this new law on general contractors, subcontractors and suppliers in both the private and public sectors will be the subject of considerable debate in the future.