< BACK
 

CIC Newsletter

articles written by Alexander A. Miuccio

2013

April 2013: Owner Precluded From Recovering Consequential Damages

March 2013: Contractor Denied Recovery For Unforseen Subsurface Conditions

February 2013: Contractual Time Limitations Bar Contractor's Extra Work Claim

January 2013: Court Rules Contractor Not Bound To Unsigned Subcontract

2012

December 2012: Contractor's Kick Back Scheme Bars Recovery For Work Performed

November 2012: Court Upholds Subcontractor's Willful Violation of Prevailing Wage Laws

October 2012: Lien Rights At Risk When Doing Business With Unlicensed Contractor

September 2012: Contractor Not Liable for Unpaid Wage Claims of Subcontractor's Workers

August 2012: Subcontractor Allowed Recovery Under Letter of Intent

July 2012: Court Dismisses Lien Claim Against Owner

June 2012: Lowest Bidder Rejected for Lack of Project Experience

May 2012: Contractor Liable for Willful Exaggeration of Lien

April 2012: Court Allows Subcontractor's Unjust Enrichment Claim

March 2012: Court Rejects Contractor's Delay Claim

February 2012: Contractor's Failure to Comply with Notice Provision Bars Extra Work Claim

January 2012: Town Violates Lowest Responsible Bidder Requirements

2011

December 2011: Corporate Agent May Be Personally Liable on Contract

November 2011: Court Rejects Concrete Supplier's Claim Against Contractor

October 2011: Court Rejects Claim for Unanticipated Increase in Cost of Materials

September 2011: Court Enforces Waiver of Lien Against Unpaid Contractor

August 2011: Contractor May Be Personally Liable for Diversion of Trust Funds

June 2011: The Pitfalls Of Stopping The Work For Nonpayment

May 2011: Court Allows Claim For Personal Liability Against Corporate Owner

April 2011: Contractor's Conduct Shows Acceptance To Terms Of Oral Contract

March 2011: Court Rules Bidder is Not Responsible

February 2011: Court Rejects Subcontractor’s Mechanic’s Lien

January 2011: Subcontractor Allowed Recovery For Work Performed

2010

December 2010: Court Allows Change Order And Extra Work Claims But Rejects Delay Claim


November 2010: Court Rejects Extra Work Claims


October 2010: Contractor Allowed To Correct Mistake After Bid Opening


September 2010: Court Rejects Variance From Bid Requirements


August 2010: Alter-Egos And Personal Liability Of Corporate Owners Are Triable Issues

July 2010: Mutual Misunderstanding Nullifies Contract

June 2010: Court Rejects "Flow-Down" Provision in Subcontract

May 2010: Court Dismisses Lien Claim Against Owner

April 2010: Court Allows Recovery for Verbal Extra Work Claim


March 2010: Short Contractual Time Period Dooms Sub's Claim


February 2010: Contractor Denied Recovery for Unforseen Site Conditions

January 2010: Court Rejects Contractor’s Delay Claim

2009

December 2009: False Vendex Statements Doom Contractor's Delay Claim


November 2009: Court Allows Contractor's Work Claim Against Architect


October 2009: Court Rules on Personal Liability Against Corporate Owner


September 2009: Subcontractor Allowed Recovery for Value of Work Performed

August 2009: Union Challenges Prevailing Wage Rate Determination

July 2009: Court Rejects Bid for Unresponsiveness

June 2009: Court Addresses Liability of Successor Company

May 2009: Court Rules on Method for Calculating Damages

April 2009: Contractual Time Limitation Bars Sub’s Claim

March 2009: Subcontractor Not Entitled to Delay Damages

February 2009 : Court Rules Owner Waived Contract Requirement for Written Extra Work

January 2009: Court Rules on Extra Work and Delay Claims

2008

December 1, 2008: Court Rejects Owner’s Claim That Contractor was Required to Bond Project

November 1, 2008: Court Rules Owner Waived Contract Requirement for Written Extra Work

October 1, 2008: Corporate Principal Personally Liable for Fringe Benefit Contributions

September 1, 2008: Subcontractor Not Entitled to Delay Damages


August 1, 2008: Court Rejects Pay-When-Paid Contract Provision

July 1, 2008: Contractor’s Pre-Bid Failure to Inspect Site Dooms Extra Work Claim

June 1, 2008: Time Limitation Does Not Bar Sub’s Claim

May 1, 2008: Court Rejects Delay Claim

April 1, 2008: Court Rejects Bid For Unresponsiveness

March 1, 2008: Trust Funds Assure Payment to Subs and Suppliers

February 1, 2008: Court Rules Contractor’s Claims are Not Time Barred

January 1, 2008: Court Rules on Measure of Damages to Repair and Complete Contract Work

2007

December 1, 2007: Contractor Allowed Recovery for Substantial Performance

November 1, 2007: Court Questions Validity of Progress Payment Releases

October 1, 2007: Summary Judgment Denied Where Subcontractor Fails to Perform

September 1, 2007: Damages Where Contractor Terminated-For-Convenience

August 1, 2007: Court Interprets Contractual Terms


July 1, 2007: Low Bidder Allowed to Correct Mistake After Bid Opening

June 1, 2007: Court Rejects Claims for Unwritten Change Order Work

May 1, 2007: Contractor Liable for Indemnification and Failure to Obtain Insurance for Owner

April 26, 2007: Safety Policy - Abatement Measures Under OSHA’s General Duty Clause

April 1, 2007: Contractual Time Limitations Dooms Sub’s Payment Bond Claim